Skip to content
Deedo home
Menu

Shri Laxmi Bhagyoday Sankul

Certificate Signed

Ambegaon Bk, Pune 411046 |Promoter: Vinay Vinayak Bhalerao

5 Jul 2019Registered with MahaRERA
31 Dec 2026Promised completion
30 Apr 2027Revised completionPushed back 4 months
1Building
23Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
—23 units in all
Address
31/3/1p 31/3/2p 31/3/2/13, Ambegaon, PunePIN 411046
Designated bank account
43
Developed in phases
No

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
5 Jul 2019
Promised
31 Dec 2026
Revised
30 Apr 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000215075 Jul 201931 Dec 202630 Apr 2027Vinay Vinayak BhaleraoProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Shri Laxmi Bhagyoday Sankul623

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

23 units registered

— · 23 units
TypeCarpet areaUnits
——23

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 172 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN CardVinay Pan card.pdf · uploaded 5 Jul 2023Source

Legal

  • Legal Title reportsearch report.pdf · uploaded 19 Jun 2019Source
  • Legal Title reportscan0276-compressed.pdf · uploaded 27 Jun 2019Source
  • Declaration Form Bscan0274.pdf · uploaded 27 Jun 2019Source
  • Declaration Form BAGREEMENT.pdf · uploaded 8 May 2026Source
  • Declaration Form BSatbara.pdf · uploaded 8 May 2026Source
Show all 174 documentsShow fewer documents

Legal

  • Declaration Form BLegal title report.pdf · uploaded 23 Jun 2026Source

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE AMBEGAON.pdf · uploaded 17 Jun 2019Source
  • 2 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE AMBEGAON_0001.pdf · uploaded 17 Jun 2019Source
  • 1 Certificates of CA (Form 3)ARCHITECT AREA STATEMENT.pdf · uploaded 17 Jun 2019Source
  • 2 Certificates of CA (Form 3)ARCHITECT AREA STATEMENT_0001.pdf · uploaded 17 Jun 2019Source
  • 1 Copy of the legal title reportsearch report.pdf · uploaded 19 Jun 2019Source
  • 2 Copy of the legal title reportsupplimentry search report.pdf · uploaded 19 Jun 2019Source
  • 1 Copy of Layout Approval (in case of layout)lay out plan.pdf · uploaded 19 Jun 2019Source
  • 1 Building Plan Approval (IOD)building plans.pdf · uploaded 19 Jun 2019Source
  • 3 Copy of the legal title reportscan0276-compressed.pdf · uploaded 27 Jun 2019Source
  • 1 Details of encumbrancesaccess mou part 1.pdf · uploaded 27 Jun 2019Source
  • 2 Details of encumbrancesaccess mou part 2.pdf · uploaded 27 Jun 2019Source
  • 3 Details of encumbrancesaccess mou part 3.pdf · uploaded 27 Jun 2019Source
  • 1 Declaration in FORM Bscan0274.pdf · uploaded 27 Jun 2019Source
  • 1 Proforma of Allotment letterallotment.pdf · uploaded 29 Jun 2019Source
  • 2 Proforma of Allotment letterAgreement to sale.pdf · uploaded 29 Jun 2019Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A.pdf · uploaded 19 Jul 2021Source
  • 3 Certificates of CA (Form 3)Form 3.pdf · uploaded 19 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5.pdf · uploaded 19 Jul 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificatte.pdf · uploaded 30 Jul 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 30 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)QA certificate.pdf · uploaded 30 Jul 2021Source
  • 1 Disclosure of sold/ booked inventoryINVENTORY 30 JUNE 2021.pdf · uploaded 30 Jul 2021Source
  • 4 Certificates of CA (Form 3)CA Cert Form 3.pdf · uploaded 30 Jul 2021Source
  • 1 Declaration about Commencement CertificateDECL ABT COMMINCEMENT CERT.pdf · uploaded 7 Oct 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE FORM 2_20211006_0001_compressed.pdf · uploaded 7 Oct 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)ENGINEERS CERTIFICATE FOR QUALITY ASSURANCE_20211005_0001_compressed.pdf · uploaded 7 Oct 2021Source
  • 2 Disclosure of sold/ booked inventoryDISCLOSURE ABOUT SOLD BOOKED INVENTORY.pdf · uploaded 7 Oct 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Certificate.pdf · uploaded 8 Oct 2021Source
  • 5 Certificates of CA (Form 3)CA REPROT 30 SEPTEMBER 2021_20211014_0001_compressed.pdf · uploaded 23 Oct 2021Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)ENGINEER'S CERTIFICATE FOR QUALITY ASSURANCE_compressed.pdf · uploaded 3 Jan 2022Source
  • 3 Disclosure of sold/ booked inventoryDISCOLSURE OF SOLD- BOOKES INVENTORY DEC-31ST,2021.pdf · uploaded 3 Jan 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers certificate form 2 Dec 2021_20220113_0001_compressed.pdf · uploaded 13 Jan 2022Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Engineers certificate for quality assurance_compressed.pdf · uploaded 13 Jan 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate form-1 14-1-2022_compressed.pdf · uploaded 28 Jan 2022Source
  • 6 Certificates of CA (Form 3)CA Certificate from -3 27-1-2022_compressed.pdf · uploaded 28 Jan 2022Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form I Arch Cer Upto compressed.pdf · uploaded 27 Apr 2022Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers certificate form 2 12 april 2022_20220413_0001_compressed (1).pdf · uploaded 3 May 2022Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quality assurance Engineers certificate form 2A 12 april 2022_20220413_0001_compressed.pdf · uploaded 3 May 2022Source
  • 4 Disclosure of sold/ booked inventoryINVENTORY SOLD UNSOLD_20220413_0001.pdf · uploaded 3 May 2022Source
  • 7 Certificates of CA (Form 3)Form 3 CA certificate_compressed.pdf · uploaded 3 May 2022Source
  • 2 Copy of Layout Approval (in case of layout)Layout plan (2).pdf · uploaded 5 May 2022Source
  • 2 Building Plan Approval (IOD)REWISED SANCTION PLAN2_compressed.pdf · uploaded 5 May 2022Source
  • 3 Building Plan Approval (IOD)REWISED SANCTION PLAN3_compressed.pdf · uploaded 5 May 2022Source
  • 3 Commencement Certificates / NA Order for plotted developmentrevised CC.pdf · uploaded 5 May 2022Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE (1).pdf · uploaded 6 Jul 2022Source
  • 6 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)ENGINEERS CERTIFICAT FOR QUALITY ASSURANCE.pdf · uploaded 6 Jul 2022Source
  • 5 Disclosure of sold/ booked inventoryDISCOLSURE OF SOLD BOOKED INVENTORY JUNE 30TH, 2022.pdf · uploaded 6 Jul 2022Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE 30TH JUNE 2022_20220719_0001 (1).pdf · uploaded 22 Jul 2022Source
  • 8 Certificates of CA (Form 3)Form 3 CA shri laxmi bhgyoday certificate .pdf · uploaded 6 Aug 2022Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE SEPTEMBER 2022_20221018_0001.pdf · uploaded 20 Oct 2022Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE FORM 2.pdf · uploaded 20 Oct 2022Source
  • 7 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)ENGINEERS CERTIFICATE FORM 2.pdf · uploaded 20 Oct 2022Source
  • 8 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)ENGINEERS CERTIFICATE QUALITY.pdf · uploaded 20 Oct 2022Source
  • 6 Disclosure of sold/ booked inventoryDISCLOSURE ABOUT SOLD BOOKED INVENTORY_20221015_0001.pdf · uploaded 20 Oct 2022Source
  • 9 Certificates of CA (Form 3)Form 3 CA CERTIFICATE (2).pdf · uploaded 20 Oct 2022Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT CERTIFICATE (3).pdf · uploaded 23 Jan 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEER CERTIFICATE_compressed.pdf · uploaded 23 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A ENGINEER CERTIFICATE FROM 2A.pdf · uploaded 23 Jan 2023Source
  • 7 Disclosure of sold/ booked inventoryINVENTORY SOLD UNSOLD FORMAT 311222-31-DEC-22.pdf · uploaded 23 Jan 2023Source
  • 10 Certificates of CA (Form 3)CA CERTIFCATE FROM 3 31-12-2022_compressed.pdf · uploaded 28 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)form 5.pdf · uploaded 28 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)ANNUAL REPORT ON STATEMENT OF ACCOUNTS FROM 5 CA CERTIFICATE 12-4-2023.pdf · uploaded 14 Apr 2023Source
  • 1 PAN CardVinay Pan card.pdf · uploaded 5 Jul 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECTS CERTIFICATE 1-APRIL 2023.pdf · uploaded 5 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)ENGINEERS CERTIFICATE FOR QUALITY ASSURANCE 31-MARCH 30-2023.pdf · uploaded 5 Jul 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)ENGINEERS CERTIFICATE FOR QUALITY ASSURANCE JUNE 26TH 2023.pdf · uploaded 5 Jul 2023Source
  • 8 Disclosure of sold/ booked inventoryDISCOLSURE OF SOLD-BOOKED INVENTORY MARCH 31-2023.pdf · uploaded 5 Jul 2023Source
  • 9 Disclosure of sold/ booked inventoryDISCOLSURE OF SOLD JUNE 30TH 2023.pdf · uploaded 5 Jul 2023Source
  • 11 Certificates of CA (Form 3)CA CERTIFICATE FROM 3 31TH MARCH 2023.pdf · uploaded 5 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)ANNUAL REPORT ON STATEMENT OF ACCOUNTS FROM 5 CA CERTIFICATE 12-4-2023.pdf · uploaded 5 Jul 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form I Architect Certificate JUNE 2023_20230713_0001.pdf · uploaded 15 Jul 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate 30th June 2023_20230715_0001.pdf · uploaded 15 Jul 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Engineers Certificate 31ST March 2023_20230715_0002.pdf · uploaded 15 Jul 2023Source
  • 12 Certificates of CA (Form 3)Form 3 C A Certificate JUNE 2023_20230713_0001.pdf · uploaded 15 Jul 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)ANNUAL REPORT ON STATEMENT OF ACCOUNTS CA FROM 5 (UT) 2022 -23.pdf · uploaded 24 Jul 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECTS CERTIFICATE 10-10-23.pdf · uploaded 8 Apr 2024Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECTS CERTIFICATE 31-DEC-2024.pdf · uploaded 8 Apr 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CARTIFICATE FROM (2) SEPTEMBER 2023.pdf · uploaded 8 Apr 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER FROM 2(1) UP TO 31 DEC 23.pdf · uploaded 8 Apr 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)ENGINEER CERTIFICATE FOR QUALITY ASSUARANCE 30 SEPTEMBER 2023.pdf · uploaded 8 Apr 2024Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)ENGINEER CERTIFICATE FOR QUALITY ASSUARANCE DECEMBER 2023.pdf · uploaded 8 Apr 2024Source
  • 10 Disclosure of sold/ booked inventoryINVENTORY SOLD UNSOLD 30 SEPTEMBER 2023.pdf · uploaded 8 Apr 2024Source
  • 11 Disclosure of sold/ booked inventoryINVENTORY SOLD UNSOLD FORMAT 311223.pdf · uploaded 8 Apr 2024Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE 31 MARCH 2024.pdf · uploaded 19 Apr 2024Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER FROM 2(1) UP TO 31 MARCH 2024.pdf · uploaded 19 Apr 2024Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)ENGINEER CERTIFICATE FOR QUALITY ASSUARANCE 31 MARCH 2024.pdf · uploaded 19 Apr 2024Source
  • 12 Disclosure of sold/ booked inventoryDISCOLSURE OF SOLD BOOKED INVENTORY 31 MARCH 2024.pdf · uploaded 19 Apr 2024Source
  • 13 Certificates of CA (Form 3)CA Cartificate from 3.pdf · uploaded 29 Apr 2024Source
  • 14 Certificates of CA (Form 3)CA cartificate ( From -3).pdf · uploaded 29 Apr 2024Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects Certificate 18-7-24.pdf · uploaded 20 Jul 2024Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERIFICATE FROM (2) JULY 24_20240717_0001.pdf · uploaded 20 Jul 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)ENGINEERS CERTIFICATE FOR QUALITY ASSURANCE FROM (2)_20240717_0001.pdf · uploaded 20 Jul 2024Source
  • 13 Disclosure of sold/ booked inventoryDISCOLSURE OF SOLD BOOKED INVENTORY JULY 2024_20240717_0001.pdf · uploaded 20 Jul 2024Source
  • 15 Certificates of CA (Form 3)From -3 CA Certificate 30 JUNE 2024.pdf · uploaded 20 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)From 1- Sep 2024.pdf · uploaded 23 Oct 2024Source
  • 2 Certificates of CA (Form 3)From 3- Sep 2024.pdf · uploaded 23 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)From 2- Sep 2024.pdf · uploaded 23 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of Sold Unsold Inventory-Sep 24.pdf · uploaded 23 Oct 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)From 2A- Sep 2024.pdf · uploaded 23 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Dec 24.pdf · uploaded 21 Jan 2025Source
  • 1 Certificates of CA (Form 3)Form 3_Dec 24.pdf · uploaded 21 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Dec 24.pdf · uploaded 21 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure_Dec 24.pdf · uploaded 21 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 21 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate March-2025.pdf · uploaded 21 Apr 2025Source
  • 1 Certificates of CA (Form 3)C A CERTIFICATE 4TH QTR.pdf · uploaded 21 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate 31-03-2025.pdf · uploaded 21 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryInventory Sold Unsold format 31032025.pdf · uploaded 21 Apr 2025Source
  • 1 Other – TechnicalEngineers certificate for Quality Assurance.pdf · uploaded 21 Apr 2025Source
  • Form 1Architect Certificate 30-06-2025.pdf · uploaded 8 Nov 2025Source
  • Form 2Engineer certificate 30-06-2025.pdf · uploaded 8 Nov 2025Source
  • Form 3RERA Certificate Q-1.pdf · uploaded 8 Nov 2025Source
  • Disclosure of Sold and Booked InventoryInventory sold unsold 30062025.pdf · uploaded 8 Nov 2025Source
  • Form 1Ar Certificate 30-09-25.pdf · uploaded 8 Nov 2025Source
  • Form 2Er Certificate 30-09-25.pdf · uploaded 8 Nov 2025Source
  • Form 3CA Certificate 30 Sept-2025.pdf · uploaded 8 Nov 2025Source
  • Disclosure of Sold and Booked InventoryInventory sold unsold 30-09-2025.pdf · uploaded 8 Nov 2025Source
  • Form 2A (FY 2019-2020)2019-2020-Form 2 A.pdf · uploaded 27 Dec 2025Source
  • Form 2A (FY 2020-2021)2020-2021-Form 2 A.pdf · uploaded 27 Dec 2025Source
  • Form 2A (FY 2021-2022)2021-2022-Form 2 A.pdf · uploaded 27 Dec 2025Source
  • Form 2A (FY 2022-2023)2022-2023-Form 2 A.pdf · uploaded 27 Dec 2025Source
  • Form 2A (FY 2023-2024)2023-2024-Form 2 A.pdf · uploaded 27 Dec 2025Source
  • Form 2A (FY 2024-2025)2024-2025-Form 2 A.pdf · uploaded 27 Dec 2025Source
  • Form 2A (FY 2024-2025)2024-2025-Form 2 A.pdf · uploaded 27 Dec 2025Source
  • Form 5 (FY 2019-2020)Form 5_FY 2019-20.pdf · uploaded 20 Feb 2026Source
  • Form 5 (FY 2020-2021)Form 5FY 2020-21.pdf · uploaded 20 Feb 2026Source
  • Form 5 (FY 2021-2022)Form 5 FY 2021-22.pdf · uploaded 20 Feb 2026Source
  • Form 5 (FY 2022-2023)Form 5 FY 2022-23.pdf · uploaded 20 Feb 2026Source
  • Form 5 (FY 2024-2025)Form 5 24_25.pdf · uploaded 20 Feb 2026Source
  • Withdrawal Update Form 1Form 1 - Dec 2025.pdf · uploaded 27 Feb 2026Source
  • Withdrawal Update Form 2Form 2 - Dec 2025.pdf · uploaded 27 Feb 2026Source
  • Withdrawal Update Form 3Form 3 - Dec 2025.pdf · uploaded 27 Feb 2026Source
  • Withdrawal Update Form 1Form 1 Architect Certificate March 2026 .pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 2Form 2 Engineers certificate March 2026 .pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 3F3 (2).pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 1Architect certificate 1st qtr 2026-2027 (2).pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 1Architect certificate 1st qtr 2026-2027 (2).pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2Engineer certificate Form 2.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2Engineer certificate Form 2.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 1F1 LBS.pdf · uploaded 8 Oct 2026Source
  • Withdrawal Update Form 1F1 LBS.pdf · uploaded 8 Oct 2026Source
  • Withdrawal Update Form 2F2 LBS.pdf · uploaded 8 Oct 2026Source
  • Withdrawal Update Form 2F2 LBS.pdf · uploaded 8 Oct 2026Source
  • Withdrawal Update Form 3Form 3 LBS.pdf · uploaded 8 Oct 2026Source
  • Withdrawal Update Form 3Form 3 LBS.pdf · uploaded 8 Oct 2026Source
  • Form 2A (FY 2025-2026)Form 2A FY 2025-2026.pdf · uploaded 8 Oct 2026Source
  • Form 5 (FY 2025-2026)Form 5 FY 2025-2026.pdf · uploaded 8 Oct 2026Source

Technical

  • Documentlay out plan.pdf · uploaded 19 Jun 2019Source
  • Documentbuilding plans.pdf · uploaded 19 Jun 2019Source
  • DocumentLayout plan (2).pdf · uploaded 5 May 2022Source
  • DocumentREWISED SANCTION PLAN2_compressed.pdf · uploaded 5 May 2022Source
  • DocumentREWISED SANCTION PLAN3_compressed.pdf · uploaded 5 May 2022Source
  • Other – TechnicalEngineers certificate for Quality Assurance.pdf · uploaded 21 Apr 2025Source
  • DocumentPlan 01.pdf · uploaded 27 Feb 2026Source
  • DocumentPlan 02.pdf · uploaded 27 Feb 2026Source

Technical (Architect)

  • DocumentFrom 1- Sep 2024.pdf · uploaded 23 Oct 2024Source
  • DocumentForm 1_Dec 24.pdf · uploaded 21 Jan 2025Source
  • DocumentArchitect Certificate March-2025.pdf · uploaded 21 Apr 2025Source
  • DocumentF1 LBS.pdf · uploaded 8 Oct 2026Source

Technical (Engineer)

  • DocumentFrom 2- Sep 2024.pdf · uploaded 23 Oct 2024Source
  • DocumentForm 2_Dec 24.pdf · uploaded 21 Jan 2025Source
  • DocumentEngineer Certificate 31-03-2025.pdf · uploaded 21 Apr 2025Source
  • DocumentF2 LBS.pdf · uploaded 8 Oct 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In AMBEGAON Bk, Haveli taluka

Survey, CTS, gat or plot numbers

31/3/1P 31/3/2P 31/3/2/13Hissa No. 3/2/13 + 31/3/2(P) + 31/3/1(P)Survey No. 31

Boundaries

North
12 Meter Wide Municipal Road
South
Survey No 31 Hissa No 3 1 P
East
Anandnagar Society
West
Survey No 31 Hissa No 3 2 P

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr Sunil D Bhamare—
Chartered accountantMr Madhav R Mate—
EngineerSuhas G Joshi—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology