Omkar Swarup Phase-2
Certificate SignedAmbegaon Bk, Pune 411046 |Promoter: Saniket Infracon LLP
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Address
- 33 Part 5a Hissa No 4 And 5, Omkar Swarup Road, Ichhapurti Ganesh MandirPIN 411046
- Designated bank account
- 76
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year
The latest completion date on record passed 1 year and 4 months ago.
- Registered
- 8 Mar 2022
- Promised
- 30 Jun 2024
- Revised
- 29 Jun 2025
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100033738 | 8 Mar 2022 | 30 Jun 2024 | 29 Jun 2025 | Saniket Infracon LLP | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Omkar Swarup Phase-II | 5 | — |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Documents
2 documents held by Deedo, 73 filings listed on MahaRERA's project page
Finance
- PAN CardSANIKET INFRACON LLP.pdf · uploaded 22 Jan 2022Source
Legal
Show all 75 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentPLAN.pdf · uploaded 22 Jan 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - REG - Jan-22.pdf · uploaded 22 Jan 2022Source
- 1 Copy of the legal title reportCOMBINED TITLE REPORT_compressed.pdf · uploaded 19 Feb 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - CA CERTIFICATE.pdf · uploaded 19 Feb 2022Source
- 1 Details of encumbrancesCERTIFICATE OF ENCUMBRANCES.pdf · uploaded 23 Feb 2022Source
- 1 Declaration about Commencement CertificateDECLARATION OF COMMENCEMENT CERTIFICATE.pdf · uploaded 23 Feb 2022Source
- 1 Declaration in FORM BFORM B - PROMOTER.pdf · uploaded 23 Feb 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM - 2 - REG - ENGINEER CERTIFICATE FEB-22.pdf · uploaded 23 Feb 2022Source
- 1 CERSAI detailsCERSAI DECLARATION.pdf · uploaded 23 Feb 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCC- 2827-2021.pdf · uploaded 3 Mar 2022Source
- 1 Proforma of Allotment letterDRAFT OF ALLOTMENT AND AGREEMENT.pdf · uploaded 3 Mar 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1- April-2022.pdf · uploaded 2 Aug 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM - 2 - REG - ENGINEER CERTIFICATE APR-22.pdf · uploaded 2 Aug 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_CA certificate_OMKARSWARUP P2 March 22_compressed (2).pdf · uploaded 2 Aug 2022Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 - July 2022_compressed.pdf · uploaded 3 Aug 2022Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 3_CA certificate_OMKARSWARUP P2 June 22_compressed.pdf · uploaded 7 Sep 2022Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3 - Sept-22.pdf · uploaded 10 Dec 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentSanction 2555-2022 - 1.pdf · uploaded 5 Jan 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentCC- 2555-2022.pdf · uploaded 5 Jan 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)आनंद गादिया आंबेगाव रेरा लेटर.pdf · uploaded 5 Jan 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 - Sept-22.pdf · uploaded 5 Jan 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 2.pdf · uploaded 25 Mar 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 1.pdf · uploaded 25 Mar 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 03.pdf · uploaded 25 Mar 2023Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MARCH 23.pdf · uploaded 15 Apr 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 March 2023.pdf · uploaded 15 Apr 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 March 2023.pdf · uploaded 15 Apr 2023Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - July 23.pdf · uploaded 12 Aug 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - July 23.pdf · uploaded 12 Aug 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - July 23_compressed.pdf · uploaded 12 Aug 2023Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1- SEPT 23.pdf · uploaded 1 Nov 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - SEPT 23.pdf · uploaded 1 Nov 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - SEPT 23_compressed.pdf · uploaded 1 Nov 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 - SEPT 2023.pdf · uploaded 1 Nov 2023Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1- JAN 24.pdf · uploaded 23 Jan 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - JAN 24.pdf · uploaded 23 Jan 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - JAN 24_compressed (1).pdf · uploaded 23 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 - SEPT 2023.pdf · uploaded 1 Mar 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - APRIL-24.pdf · uploaded 17 Apr 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - APRIL-24.pdf · uploaded 17 Apr 2024Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM - 1 APRIL - 24.pdf · uploaded 19 Apr 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_CA certificate - JULY 24.pdf · uploaded 11 Jul 2024Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - July 2024.pdf · uploaded 8 Aug 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A 21-22.pdf · uploaded 8 Aug 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 22-23.pdf · uploaded 8 Aug 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 23-24.pdf · uploaded 8 Aug 2024Source
- 1 Disclosure of sold/ booked inventoryCircular 29.pdf · uploaded 8 Aug 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure - A.pdf · uploaded 8 Aug 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format - A.pdf · uploaded 8 Aug 2024Source
- 2 Declaration in FORM BForm B (2).pdf · uploaded 9 Aug 2024Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - July 2024_11zon.pdf · uploaded 9 Aug 2024Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 - Sept 23.pdf · uploaded 9 Aug 2024Source
- 2 Architect’s Certificate on Completion of Project (Form 4)FORM- 4 - COMPLETION.pdf · uploaded 19 Dec 2024Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate- Final Both.pdf · uploaded 19 Dec 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5- FY-23-24.pdf · uploaded 19 Dec 2024Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5- FY-23-24.pdf · uploaded 19 Dec 2024Source
- 3 Architect’s Certificate on Completion of Project (Form 4)Form 4 - Architect.pdf · uploaded 28 Dec 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 - Architect Dec-24.pdf · uploaded 2 Jan 2025Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate- 2.pdf · uploaded 2 Jan 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentCC - 2440-2024 -.pdf · uploaded 13 Jan 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentCC-2440-2024.pdf · uploaded 13 Jan 2025Source
Technical
Technical (Architect)
- DocumentForm 1 - July 2024.pdf · uploaded 8 Aug 2024Source
Technical (Engineer)
- DocumentFORM 2 - APRIL-24.pdf · uploaded 17 Apr 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In AMBEGAON Bk, Haveli taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- 33 Part 5a Hissa 2
- South
- 33 Part 5a
- East
- 33 Part 5b
- West
- Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Anand Gadiya | — |
| Chartered accountant | Hnv And Co | — |
| Engineer | Gaurav D Shah | — |
| Engineer | Harsh Raleraskar | — |
| Other | Ananta Amrutkar | — |
| Other | G A Bhilare Consultants Pvt Ltd | — |
| Other | Phoenix Consultant | — |
| Registered real estate agent | Mayur Nimba Rane | — |
Source: MahaRERA project page. Contact details are not shown.