A1 Complex
Its promised completion date, Mar 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 39% of its units are booked.
Vasai, Maharashtra 401208 · Promoter: A.1. Real Estate
Its promised completion date, Mar 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 18 Mar 2020, completion promised 30 Mar 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- A1 Complex Building No 22 floors · 9 units89% booked
- A1 Complex Building No 31 floor · 3 units100% booked
- A1 Complex Cfc Building2 floors · 16 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP99000025038
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000025038 | 18 Mar 2020 | 30 Mar 2024 | 30 Mar 2024 | A.1. Real Estate | Project page |
Documents36
1 document held by Deedo, 35 filings listed on MahaRERA's project page
Finance
- PAN CardPAN.pdf · uploaded 9 Mar 2020Source
Legal
Show all 36 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesENCUMBRANCE.pdf · uploaded 9 Mar 2020Source
- 1 Copy of Layout Approval (in case of layout)LAY OUT.pdf · uploaded 9 Mar 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN PAGE-3.pdf · uploaded 9 Mar 2020Source
- 2 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN PAGE-4.pdf · uploaded 9 Mar 2020Source
- 3 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN 5.pdf · uploaded 9 Mar 2020Source
- 4 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN 6.pdf · uploaded 9 Mar 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 9 Mar 2020Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 9 Mar 2020Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 9 Mar 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2.pdf · uploaded 9 Mar 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 9 Mar 2020Source
- 1 Proforma of Allotment letterSALE AGREEMNT DRAFT COPY.pdf · uploaded 9 Mar 2020Source
- 1 OtherOTHER CLARIFICATION.pdf · uploaded 9 Mar 2020Source
- 2 OtherPA.pdf · uploaded 9 Mar 2020Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3.pdf · uploaded 5 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM-5.pdf · uploaded 5 Oct 2021Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3.pdf · uploaded 23 Nov 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM-5 FY 2021-22.pdf · uploaded 23 Nov 2022Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC-1.pdf · uploaded 23 Nov 2022Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC-2.pdf · uploaded 23 Nov 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM-5 FY 2019-20.pdf · uploaded 11 Apr 2023Source
Technical
Technical (Architect)
- DocumentFORM-1.pdf · uploaded 9 Mar 2020Source
Technical (Engineer)
- DocumentFORM-2.pdf · uploaded 9 Mar 2020Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals
As registered with MahaRERA and published on its project page
- Project type
- Commercial
- Status on MahaRERA
- Certificate Signed
- Unit types
- Unit28 units in all
- Address
- S No 1, Hissa No.2, Kaman Road, KamanPIN 401208
- Developed in phases
- Yes
Boundaries
- North
- Sn No 2
- South
- Sn No 1
- East
- Sn No 63
- West
- Sn No 4
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking28 units
11 of 28 units booked (39%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| A1 Complex Building No 2 | Unit | 112 sq m · 1,206 sq ft | 5 | 5 |
| A1 Complex Building No 2 | Unit | 113.34 sq m · 1,220 sq ft | 2 | 2 |
| A1 Complex Building No 2 | Unit | 113.81 sq m · 1,225 sq ft | 2 | 1 |
| A1 Complex Building No 3 | Unit | 28.8 sq m · 310 sq ft | 1 | 1 |
| A1 Complex Building No 3 | Unit | 35.77 sq m · 385 sq ft | 2 | 2 |
| A1 Complex Cfc Building | Unit | 17.19 sq m · 185 sq ft | 2 | 0 |
| A1 Complex Cfc Building | Unit | 17.65 sq m · 190 sq ft | 3 | 0 |
| A1 Complex Cfc Building | Unit | 18.12 sq m · 195 sq ft | 2 | 0 |
| A1 Complex Cfc Building | Unit | 19.97 sq m · 215 sq ft | 9 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Himesh Gupta | — |
| Chartered accountant | Ajay Vaghasia | — |
| Engineer | Mohd Sufiyan Shaikh | — |
| Other | Javed Faruque | — |
Source: MahaRERA project page. Contact details are not shown.