Extended 32 mo4 floorsRERA P99000028979

Main building, Kgn Complex

Deedo IDDP-PAL-RJKQ-KC

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

Median saleNot on recordneeds 3 or more sales
Booked0%0 of 41 · MahaRERA
Completion30 Sep 202631 Jan 2024 · revised
Units & parking in Main building
TypeCarpet areaUnitsBooked
1BHK37 m² (398 sq.ft)30
1BHK37.6 m² (405 sq.ft)20
1BHK38.1 m² (410 sq.ft)20
1BHK38.5 m² (414 sq.ft)50
1BHK39.9 m² (429 sq.ft)20
1BHK40 m² (431 sq.ft)30
1RK23.3 m² (251 sq.ft)30
2BHK49.7 m² (535 sq.ft)30
2BHK51.7 m² (557 sq.ft)20
Shop7.5 m² (80 sq.ft)20
Shop7.6 m² (82 sq.ft)10
Shop9.2 m² (99 sq.ft)30
Shop9.9 m² (107 sq.ft)10
Shop10.9 m² (117 sq.ft)10
Shop13.2 m² (142 sq.ft)10
Shop19.1 m² (206 sq.ft)10
Shop22.1 m² (238 sq.ft)10
Shop22.7 m² (244 sq.ft)10
Shop24.8 m² (267 sq.ft)10
Shop24.9 m² (268 sq.ft)10
Shop27 m² (291 sq.ft)10
Shop35.3 m² (380 sq.ft)10
As registered with MahaRERA
RERA registration
P99000028979 · registered 23 Apr 2021
Promised completion
31 Jan 2024
Revised completion
30 Sep 2026
Sanctioned habitable floors
4
Building
KGN COMPLEX
Sanctioned floors (incl. basement, stilt, podium)
4
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
Deedo IDDP-PAL-RJKQ-KC
Questions about Main building

When is Main building due for completion?

The MahaRERA registration promises 31 Jan 2024, revised to 30 Sep 2026.

How many floors does Main building have?

4 sanctioned habitable floors, as registered with MahaRERA.

Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Methodology