Its promised completion date, Sep 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Pasthal, Palghar 401501 · Promoter: Shree Adinath Builders

Delivery2 yrs 1 mo past duePromised Sep 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 18 units · as the promoter reported to MahaRERA
Symphony D Wing project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Sep 2024, has passed and MahaRERA does not show it completed

  • This projectRegistered 30 Sep 2019, completion promised 30 Sep 2024, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000022509
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900002250930 Sep 201930 Sep 202430 Sep 2024Shree Adinath BuildersProject page
Documents24

1 document held by Deedo, 23 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardSAB Pan Card S.pdf · uploaded 11 Sep 2019Source

Legal

  • Legal Title reportSymphony Title Certificate Compressed.pdf · uploaded 11 Sep 2019Source
  • Declaration Form BDeclaration.pdf · uploaded 24 Sep 2019Source

Migrated

  • 1 PAN CardSAB Pan Card S.pdf · uploaded 11 Sep 2019Source
  • 1 Copy of the legal title reportSymphony Title Certificate Compressed.pdf · uploaded 11 Sep 2019Source
  • 1 Details of encumbrancesNo Encumberence.pdf · uploaded 11 Sep 2019Source
  • 1 Copy of Layout Approval (in case of layout)01-LAYOUT.pdf · uploaded 11 Sep 2019Source
Show all 24 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentBoisar- Type D1.pdf · uploaded 11 Sep 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentBoisar CC.pdf · uploaded 11 Sep 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Nishant Patil D wing RERA certificate 05_07_19_compressed.pdf · uploaded 11 Sep 2019Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate D Wing.pdf · uploaded 11 Sep 2019Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate D Wing.pdf · uploaded 11 Sep 2019Source
  • 1 Proforma of Allotment letterAllotment Letter All in one.pdf · uploaded 11 Sep 2019Source
  • 2 Proforma of Allotment letterdownload.pdf · uploaded 11 Sep 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentSymphony Wing A B C D Plinth CC_compressed.pdf · uploaded 11 Sep 2019Source
  • 1 Declaration in FORM BDeclaration.pdf · uploaded 24 Sep 2019Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Final Certificate D Wing .pdf · uploaded 14 Mar 2022Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentBldg No 4 OC Certificate Symphony Boisar (1).pdf · uploaded 17 Aug 2022Source
  • 5 Architect’s Certificate on Completion of Project (Form 4)RERA Form 4 D Wing - Nishant Patil (2).pdf · uploaded 17 Aug 2022Source

Technical

  • Document01-LAYOUT.pdf · uploaded 11 Sep 2019Source
  • DocumentBoisar- Type D1.pdf · uploaded 11 Sep 2019Source

Technical (Architect)

  • DocumentNishant Patil D wing RERA certificate 05_07_19_compressed.pdf · uploaded 11 Sep 2019Source

Technical (Engineer)

  • DocumentEngineer Certificate D Wing.pdf · uploaded 11 Sep 2019Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals61/1/10, 61/1/4/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK18 units in all
Address
61/1/4/1, 61/1/6, 61/1/7, 61/1/8, 61/1/9, 61/1/10, 63/1, 63/3, 63/4, Boisar, BoisarPIN 401501
Village
pasthal, Palghar taluka
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

61/1/1061/1/4/161/1/661/1/761/1/861/1/963/163/363/4

Boundaries

North
9 Meter Layout Road
South
Survey No 61-1 Pasthal
East
Survey No 61-1 Pasthal
West
12 Meter Layout Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking18 units

0 of 18 units booked (0%), as the promoter reported to MahaRERA

1BHK · 13 units2BHK · 5 units
TypeCarpet areaUnitsBooked
1BHK30.79 sq m · 331 sq ft130
2BHK38.48 sq m · 414 sq ft50

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectNishant Prabhakar Patil—
Chartered accountantAjay Shah & Co—
EngineerDarsh Consult—
OtherKhodiyar Construction—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology