Residential / Group Housing · 2 buildings · 46 unitsRERA P99000017032

Parshv Glory

Deedo IDDP-PAL-T9WC

Completion was pushed back 5 years and 4 months to Dec 2024, and that date has passed too; no MahaRERA orders on record; 83% of its units are booked.

Mahim, Palghar 401404 · Promoter: Jinit Ramesh Mehta

Delivery7 yrs 2 mo latePromised Aug 2019 · revised Dec 2024 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales83% booked38 of 46 units · as the promoter reported to MahaRERA
Parshv Glory project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 5 years and 4 months to Dec 2024, and that date has passed too

  • This projectRegistered 4 Jul 2018, completion promised 31 Aug 2019, revised to 31 Dec 2024, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000017032
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P990000170324 Jul 201831 Aug 201931 Dec 2024Jinit Ramesh MehtaProject page
Documents78

2 documents held by Deedo, 76 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN Cardilovepdf_jpg_to_pdf.pdf · uploaded 16 Jun 2018Source

Legal

  • Declaration Form B20180619152012.pdf · uploaded 19 Jun 2018Source
  • Legal Title report20180620184507.pdf · uploaded 20 Jun 2018Source
  • Declaration Form BFORM B_11zon.pdf · uploaded 12 Jan 2024Source
  • Declaration Form BForm B - Jinit Mehta.pdf · uploaded 29 Jan 2024Source
  • Declaration Form BForm B (With Date).pdf · uploaded 9 Feb 2024Source
Show all 78 documentsShow fewer documents

Migrated

  • 1 PAN Cardilovepdf_jpg_to_pdf.pdf · uploaded 16 Jun 2018Source
  • 1 Copy of Layout Approval (in case of layout)MYSCAN_20180615_0002.pdf · uploaded 16 Jun 2018Source
  • 1 Building Plan Approval (IOD)MYSCAN_20180615_0001.pdf · uploaded 16 Jun 2018Source
  • 2 Building Plan Approval (IOD)CC PARSHV GLORY.pdf · uploaded 16 Jun 2018Source
  • 1 Details of encumbrancesPASRHV DEVELOPERS LETTER.pdf · uploaded 18 Jun 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC PARSHV GLORY.pdf · uploaded 18 Jun 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)VASTU SHILP ARTICTE'S CERTIFICATE.pdf · uploaded 18 Jun 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)DARSH CONSULTANT.pdf · uploaded 18 Jun 2018Source
  • 1 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 18 Jun 2018Source
  • 1 Declaration in FORM B20180619152012.pdf · uploaded 19 Jun 2018Source
  • 1 Proforma of Allotment letter20180619151929.pdf · uploaded 19 Jun 2018Source
  • 1 Copy of the legal title report20180620184507.pdf · uploaded 20 Jun 2018Source
  • 2 Proforma of Allotment lettersale of agreement of parshv glory.pdf · uploaded 26 Nov 2018Source
  • 3 Proforma of Allotment letterLETTER OF ALLOTMENT PDF.pdf · uploaded 26 Nov 2018Source
  • 1 Annual Audit Report of Statutory CA (Form 5)ANNUAL REPORT FORM 5.pdf · uploaded 17 Oct 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentWORK COMPLETED CERTIFICATE.pdf · uploaded 29 Nov 2019Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4 PARSHV GLORY.pdf · uploaded 6 Feb 2020Source
  • 2 Declaration in FORM BFORM B_11zon.pdf · uploaded 12 Jan 2024Source
  • 1 CERSAI detailsCERSAI_Search_Report_200293012603_For_Asset_Based_Search_09_01_2024_16_16_29_811.pdf · uploaded 12 Jan 2024Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 12 Jan 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMAT A.pdf · uploaded 12 Jan 2024Source
  • 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 29 Jan 2024Source
  • 3 Declaration in FORM BForm B - Jinit Mehta.pdf · uploaded 29 Jan 2024Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)As on 31 Mar 2021.pdf · uploaded 29 Jan 2024Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)As on 30 June 2022.pdf · uploaded 29 Jan 2024Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)As on 30 Sept 2022.pdf · uploaded 29 Jan 2024Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)As on 31 Dec 2022.pdf · uploaded 29 Jan 2024Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)As on 31 Mar 2023.pdf · uploaded 29 Jan 2024Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)As on 30 June 2023.pdf · uploaded 29 Jan 2024Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)As on 30 Sept 2023.pdf · uploaded 29 Jan 2024Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)As on 31 Dec 2023.pdf · uploaded 29 Jan 2024Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)As on 31-03-2019.pdf · uploaded 29 Jan 2024Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)As on 31-03-2020.pdf · uploaded 29 Jan 2024Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)As on 31-03-2021.pdf · uploaded 29 Jan 2024Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)As on 31-03-2022.pdf · uploaded 29 Jan 2024Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)As on 30-06-2022.pdf · uploaded 29 Jan 2024Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)As on 30-09-2022.pdf · uploaded 29 Jan 2024Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)As on 31-12-2022.pdf · uploaded 29 Jan 2024Source
  • 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)As on 31-03-2023.pdf · uploaded 29 Jan 2024Source
  • 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)As on 31-06-2023.pdf · uploaded 29 Jan 2024Source
  • 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)As on 30-09-2023.pdf · uploaded 29 Jan 2024Source
  • 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)As on 31-12-2023.pdf · uploaded 29 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Certificate For FY 2019-2020.pdf · uploaded 29 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Certificate For FY 2020-2021.pdf · uploaded 29 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Certificate For FY 2021-2022.pdf · uploaded 29 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Certificate For FY 2022-2023.pdf · uploaded 29 Jan 2024Source
  • 2 Certificates of CA (Form 3)As on 31032019.pdf · uploaded 29 Jan 2024Source
  • 3 Certificates of CA (Form 3)As on 31032020.pdf · uploaded 29 Jan 2024Source
  • 4 Certificates of CA (Form 3)As on 31032021.pdf · uploaded 29 Jan 2024Source
  • 5 Certificates of CA (Form 3)As on 31-03-2022(C).pdf · uploaded 29 Jan 2024Source
  • 6 Certificates of CA (Form 3)As on 30-06-2022(C).pdf · uploaded 29 Jan 2024Source
  • 7 Certificates of CA (Form 3)As on 30-09-2022(C).pdf · uploaded 29 Jan 2024Source
  • 8 Certificates of CA (Form 3)As on 31-12-2022(C).pdf · uploaded 29 Jan 2024Source
  • 9 Certificates of CA (Form 3)As on 31-03-2023(C).pdf · uploaded 29 Jan 2024Source
  • 10 Certificates of CA (Form 3)As on 30-06-2023(C).pdf · uploaded 29 Jan 2024Source
  • 11 Certificates of CA (Form 3)As on 30-09-2023(C).pdf · uploaded 29 Jan 2024Source
  • 12 Certificates of CA (Form 3)As on 31-12-2023(C).pdf · uploaded 29 Jan 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDeclaration about Interest in Real Estate - Jinit Mehta.pdf · uploaded 29 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FY 01-04-2019 to 31-03-2020.pdf · uploaded 29 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FY 01-04-2020 to 31-03-2021.pdf · uploaded 29 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FY 01-04-2021 to 31-03-2022.pdf · uploaded 29 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FY 01-04-2022 to 31-03-2023.pdf · uploaded 29 Jan 2024Source
  • 1 Proforma of Agreement for saleag1.pdf · uploaded 29 Jan 2024Source
  • 2 Proforma of Agreement for saleag2.pdf · uploaded 29 Jan 2024Source
  • 4 Declaration in FORM BForm B (With Date).pdf · uploaded 9 Feb 2024Source

Technical

  • DocumentMYSCAN_20180615_0001.pdf · uploaded 16 Jun 2018Source
  • DocumentCC PARSHV GLORY.pdf · uploaded 16 Jun 2018Source
  • DocumentMYSCAN_20180615_0002.pdf · uploaded 16 Jun 2018Source

Technical (Architect)

  • DocumentAs on 31 Dec 2023.pdf · uploaded 29 Jan 2024Source

Technical (Engineer)

  • DocumentAs on 31-12-2023.pdf · uploaded 29 Jan 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals404/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK46 units in all
Address
404/1, Wagulsar, Mahim VillagePIN 401404
Village
Mahim, Palghar taluka
Designated bank account
51
Developed in phases
Yes

Survey, CTS, gat or plot numbers

404/1

Boundaries

North
Internal Layout Road
South
S No 402-1
East
Building No 5
West
S No 405

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking46 units

38 of 46 units booked (83%), as the promoter reported to MahaRERA

1BHK · 39 units2BHK · 7 units
BuildingTypeCarpet areaUnitsBooked
Wing C1BHK28.88 sq m · 311 sq ft22
Wing C1BHK29.09 sq m · 313 sq ft11
Wing C1BHK30.55 sq m · 329 sq ft22
Wing C1BHK30.78 sq m · 331 sq ft87
Wing C2BHK42.38 sq m · 456 sq ft10
Wing C2BHK44.68 sq m · 481 sq ft22
Wing D1BHK30.08 sq m · 324 sq ft11
Wing D1BHK30.55 sq m · 329 sq ft21
Show all 13 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Wing D1BHK30.78 sq m · 331 sq ft84
Wing D1BHK31.89 sq m · 343 sq ft1211
Wing D1BHK36.93 sq m · 398 sq ft11
Wing D1BHK44.68 sq m · 481 sq ft22
Wing D2BHK38.89 sq m · 419 sq ft44

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVastu Shilp Associates—
Chartered accountantBharat Dhonde and Co—
EngineerDarsh Consult—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology