Residential / Group Housing · 1 building · 14 unitsRERA PR1220002501451

Ayodhya

It is due for completion in Dec 2027, with no extension on record; no MahaRERA orders on record; 7% of its units are booked.

Nashik 422009 · Promoter: S R Developers

DeliveryDue Dec 2027No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales7% booked1 of 14 units · as the promoter reported to MahaRERA
Ayodhya project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

It is due for completion in Dec 2027, with no extension on record

  • This projectRegistered 13 Nov 2025, completion promised 31 Dec 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPR1220002501451
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR122000250145113 Nov 202531 Dec 202731 Dec 2027S R DevelopersProject page
Documents16

1 document held by Deedo, 15 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPatnership firm pan.pdf · uploaded 15 Oct 2025Source

Legal

  • OthersDisclousre of intrest.pdf · uploaded 15 Oct 2025Source
  • Declaration Form BLegal Title Report.pdf · uploaded 15 Oct 2025Source
  • Declaration Form BForm B SR.pdf · uploaded 15 Oct 2025Source
  • Declaration Form B7 12.pdf · uploaded 15 Oct 2025Source

Migrated

  • Withdrawal Update Form 1SR Developers (Fom-1)_0001.pdf · uploaded 27 Feb 2026Source
  • Withdrawal Update Form 2SR Deelopers (Form-2 Ayodhya)_0001.pdf · uploaded 27 Feb 2026Source
Show all 16 documentsShow fewer documents

Migrated

  • Withdrawal Update Form 3SR developers (Form-3 Ayodhya)_0001.pdf · uploaded 27 Feb 2026Source
  • Withdrawal Update Form 1S R Developers Form 1.pdf · uploaded 3 Jun 2026Source
  • Withdrawal Update Form 2S R Developers Form 2.pdf · uploaded 3 Jun 2026Source
  • Withdrawal Update Form 3S R Developers Form 3.pdf · uploaded 3 Jun 2026Source

Technical

  • DocumentApproved Plan.pdf · uploaded 15 Oct 2025Source
  • DocumentAnnexure A Declaration Cum Undertaking.pdf · uploaded 3 Nov 2025Source

Technical (Architect)

  • DocumentS R Developers Form 1.pdf · uploaded 3 Jun 2026Source

Technical (Engineer)

  • DocumentS R Developers Form 2.pdf · uploaded 3 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsP. NO. 5 OF S. NO. 874/6/3/5/PLOT/5 AT NASHIK SHIWAR

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—14 units in all
Address
P. No. 5 Of S.no. 874/6/3/5/Plot/5 Nashik Shiwar - Nashik, ShiwarPIN 422009
Village
Nashik, Nashik taluka
Designated bank account
17
Developed in phases
No

Survey, CTS, gat or plot numbers

P. NO. 5 OF S. NO. 874/6/3/5/PLOT/5 AT NASHIK SHIWAR

Boundaries

North
Modakeshwar Colony
South
Colony Road
East
Plot No. 6
West
Plot No.4

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking14 units

14 units registered

— · 14 units
TypeCarpet areaUnits
——14

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDnyanesh Bapat—
Chartered accountantBhavana Bhushan Loya—
Chartered accountantCA Bhavana Loya—
EngineerSiddharth Suryawanshi—

Source: MahaRERA project page. Contact details are not shown.