Skip to content
Residential / Group Housing · 1 buildingRERA P51600077790

Green Heritage

Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record.

Deolali (Cb), Nashik 422101 · Promoter: Kusheja Builders And Developers Private Limited

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has read
Green Heritage project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 30 Oct 2024, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51600077790
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160007779030 Oct 202431 Dec 202830 Apr 2029Kusheja Builders And Developers Private LimitedProject page
Documents39

1 document held by Deedo, 38 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Card1 PAN.pdf · uploaded 25 Jun 2024Source

Legal

  • Other – Legal34 KUSHEJA sale deed_upload.pdf · uploaded 25 Jun 2024Source
  • Declaration Form B9 Form B.pdf · uploaded 25 Jun 2024Source
  • Legal Title report2 Scan Rera Title Report_upload.pdf · uploaded 25 Jun 2024Source

Migrated

  • 1 PAN Card1 PAN.pdf · uploaded 25 Jun 2024Source
  • 1 Copy of the legal title report2 Scan Rera Title Report_upload.pdf · uploaded 25 Jun 2024Source
  • 1 a Details of encumbrances concerned to FinanceNo litigation.pdf · uploaded 25 Jun 2024Source
Show all 39 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)5 Copy of Leyout approval.pdf · uploaded 25 Jun 2024Source
  • 1 Declaration in FORM B9 Form B.pdf · uploaded 25 Jun 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)10 Form 1.pdf · uploaded 25 Jun 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)19 Form 3 CA RERA certificate_upload.pdf · uploaded 25 Jun 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)11 Form 2.pdf · uploaded 25 Jun 2024Source
  • 1 Commencement Certificates / NA Order for plotted development7 Commencement Certificate.pdf · uploaded 25 Jun 2024Source
  • 1 Building Plan Approval / NA Order for plotted development6 Plan_upload.pdf · uploaded 25 Jun 2024Source
  • 1 Other – Legal34 KUSHEJA sale deed_upload.pdf · uploaded 25 Jun 2024Source
  • 1 Disclosure of sold/ booked inventory17 Disclosure of Sold _ Booked Inventory.pdf · uploaded 25 Jun 2024Source
  • 1 CERSAI details18 Cersai declaration.pdf · uploaded 25 Jun 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same38 Separate Bank Account.pdf · uploaded 25 Jun 2024Source
  • 1 b Details of encumbrances concerned to LegalNo litigation.pdf · uploaded 25 Jun 2024Source
  • 1 Other – Technical36 Annexure A Declaration Cum Undertaking.pdf · uploaded 25 Jun 2024Source
  • 1 Proforma of Allotment letter30 Model Allotement Letter.pdf · uploaded 5 Jul 2024Source
  • 1 Deviation Report with respect to Allotment letter38 No Deviation Allotment letter.pdf · uploaded 5 Jul 2024Source
  • 1 Deviation Report with respect to model copy of Agreement39 No Deviation Agreement for sale.pdf · uploaded 5 Jul 2024Source
  • 1 Proforma of Agreement for sale29 Model Agreement.pdf · uploaded 5 Jul 2024Source
  • 1 Disclosure of Interest in Other Real Estate Organizations19 disclosure of interest in other organisation.pdf · uploaded 5 Jul 2024Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 29 Jul 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 as on 31032024.pdf · uploaded 1 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 as on 31032024.pdf · uploaded 1 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 22 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 22 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 22 Jan 2025Source

Technical

  • Document6 Plan_upload.pdf · uploaded 25 Jun 2024Source
  • Document5 Copy of Leyout approval.pdf · uploaded 25 Jun 2024Source
  • Other – Technical36 Annexure A Declaration Cum Undertaking.pdf · uploaded 25 Jun 2024Source

Technical (Architect)

  • Document10 Form 1.pdf · uploaded 25 Jun 2024Source
  • DocumentForm 1.pdf · uploaded 22 Jan 2025Source

Technical (Engineer)

  • Document11 Form 2.pdf · uploaded 25 Jun 2024Source
  • DocumentForm 2.pdf · uploaded 22 Jan 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsPLOT NO. 2 OF S. NO. 45/11 (P)

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Address
Plot No. 2 Of S. No. 45/11 (P), Deolali Camp, Nashik RoadPIN 422101
Village
Deolali (CB), Nashik taluka
Designated bank account
229
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO. 2 OF S. NO. 45/11 (P)

Boundaries

North
18 Meter Road
South
Hari Krishna Phase 3
East
S No 45-12
West
S No 45-10

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Rasik Shankarlal Bothra—
Chartered accountantSushil Sakhare & Co Proprietor Cas Sushil Sadashiv Sakhare—
EngineerSunil Patel—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology