Skip to content
Deedo home
Menu

Ramanuj

Active

Nanded Waghala (M Corp.), Nanded 413605 |Promoter: Shri Tirumala Civil Work Pvt Ltd

Residential / Group HousingRERAP51100077007
16 Jul 2024Registered with MahaRERA
31 Dec 2028Promised completion
60Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Active
Buildings
60
Land area for this project
7,535 sq m (81,106 sq ft)
Permissible built-up area
8,240 sq m (88,698 sq ft)
Sanctioned built-up area
8,240 sq m (88,698 sq ft)
Recreational open space
0 sq m (0 sq ft)
Planning authority
Tahsildar Nanded
Address
Plots No 12, 13, 118 to 147, 150 to 155 158 to 165, 168 to 178, Sy No. 38/A/1/1, situated at mauje Wadi(BK), Nanded 413605, Wadi(BK), NandedPIN 413605
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Ramanuj is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2028

Registered
16 Jul 2024
Promised
31 Dec 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5110007700716 Jul 202431 Dec 2028—Shri Tirumala Civil Work Pvt LtdProject page

60 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Row House No 01 Plot No 122—
Row House No 02 Plot No 132—
Row House No 03 Plot No 1182—
Row House No 04 Plot No 1192—
Row House No 05 Plot No 1202—
Row House No 06 Plot No 1212—
Row House No 07 Plot No 1222—
Row House No 08 Plot No 1232—
Row House No 09 Plot No 1242—
Row House No 10 Plot No 1252—
Row House No 11 Plot No 1262—
Row House No 12 Plot No 1272—
Row House No 13 Plot No 1282—
Row House No 14 Plot No 1292—
Row House No 15 Plot No 1302—
Row House No 16 Plot No 1312—
Row House No 17 Plot No 1322—
Row House No 18 Plot No 1332—
Row House No 19 Plot No 1342—
Row House No 20 Plot No 1352—
Row House No 21 Plot No 1362—
Row House No 22 Plot No 1362—
Row House No 23 Plot No 1582—
Row House No 24 Plot No 1592—
Row House No 25 Plot No 1602—
Row House No 26 Plot No 1602—
Row House No 27 Plot No 1612—
Row House No 28 Plot No 1622—
Row House No 29 Plot No 1632—
Row House No 30 Plot No 1642—
Row House No 31 Plot No 1652—
Row House No 32 Plot No 1682—
Row House No 33 Plot No 1692—
Row House No 34 Plot No 1702—
Row House No 35 Plot No 1712—
Row House No 36 Plot No 1722—
Row House No 37 Plot No 1732—
Row House No 38 Plot No 1742—
Row House No 39 Plot No 1752—
Row House No 40 Plot No 1762—
Row House No 41 Plot No 1772—
Row House No 42 Plot No 1782—
Row House No 43 Plot No 1372—
Row House No 44 Plot No 1382—
Row House No 45 Plot No 1392—
Row House No 46 Plot No 1402—
Row House No 47 Plot No 1412—
Row House No 48 Plot No 1422—
Row House No 49 Plot No 1432—
Row House No 50 Plot No 1442—
Row House No 51 Plot No 1452—
Row House No 52 Plot No 1462—
Row House No 53 Plot No 1472—
Row House No 54 Plot No 1502—
Row House No 55 Plot No 1512—
Row House No 56 Plot No 1522—
Row House No 57 Plot No 1532—
Row House No 58 Plot No 1542—
Row House No 59 Plot No 1552—
Row House No 60 Plot No 1562—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Row House No 01 Plot No 12Closed/Covered00000
Row House No 01 Plot No 12Open Space00000
Row House No 02 Plot No 13Closed/Covered00000
Row House No 02 Plot No 13Open Space00000
Row House No 03 Plot No 118Closed/Covered00000
Row House No 03 Plot No 118Open Space00000
Row House No 04 Plot No 119Closed/Covered00000
Row House No 04 Plot No 119Open Space00000
Row House No 05 Plot No 120Closed/Covered00000
Row House No 05 Plot No 120Open Space00000
Row House No 06 Plot No 121Closed/Covered00000
Row House No 06 Plot No 121Open Space00000
Row House No 07 Plot No 122Closed/Covered00000
Row House No 07 Plot No 122Open Space00000
Row House No 08 Plot No 123Closed/Covered00000
Row House No 08 Plot No 123Open Space00000
Row House No 09 Plot No 124Closed/Covered00000
Row House No 09 Plot No 124Open Space00000
Row House No 10 Plot No 125Closed/Covered00000
Row House No 10 Plot No 125Open Space00000
Row House No 11 Plot No 126Closed/Covered00000
Row House No 11 Plot No 126Open Space00000
Row House No 12 Plot No 127Closed/Covered00000
Row House No 12 Plot No 127Open Space00000
Row House No 13 Plot No 128Closed/Covered00000
Row House No 13 Plot No 128Open Space00000
Row House No 14 Plot No 129Closed/Covered00000
Row House No 14 Plot No 129Open Space00000
Row House No 15 Plot No 130Closed/Covered00000
Row House No 15 Plot No 130Open Space00000
Row House No 16 Plot No 131Closed/Covered00000
Row House No 16 Plot No 131Open Space00000
Row House No 17 Plot No 132Closed/Covered00000
Row House No 17 Plot No 132Open Space00000
Row House No 18 Plot No 133Closed/Covered00000
Row House No 18 Plot No 133Open Space00000
Row House No 19 Plot No 134Closed/Covered00000
Row House No 19 Plot No 134Open Space00000
Row House No 20 Plot No 135Closed/Covered00000
Row House No 20 Plot No 135Open Space00000
Row House No 21 Plot No 136Closed/Covered00000
Row House No 21 Plot No 136Open Space00000
Row House No 22 Plot No 136Closed/Covered00000
Row House No 22 Plot No 136Open Space00000
Row House No 23 Plot No 158Closed/Covered00000
Row House No 23 Plot No 158Open Space00000
Row House No 24 Plot No 159Closed/Covered00000
Row House No 24 Plot No 159Open Space00000
Row House No 25 Plot No 160Closed/Covered00000
Row House No 25 Plot No 160Open Space00000
Row House No 26 Plot No 160Closed/Covered00000
Row House No 26 Plot No 160Open Space00000
Row House No 27 Plot No 161Closed/Covered00000
Row House No 27 Plot No 161Open Space00000
Row House No 28 Plot No 162Closed/Covered00000
Row House No 28 Plot No 162Open Space00000
Row House No 29 Plot No 163Closed/Covered00000
Row House No 29 Plot No 163Open Space00000
Row House No 30 Plot No 164Closed/Covered00000
Row House No 30 Plot No 164Open Space00000
Row House No 31 Plot No 165Closed/Covered00000
Row House No 31 Plot No 165Open Space00000
Row House No 32 Plot No 168Closed/Covered00000
Row House No 32 Plot No 168Open Space00000
Row House No 33 Plot No 169Closed/Covered00000
Row House No 33 Plot No 169Open Space00000
Row House No 34 Plot No 170Closed/Covered00000
Row House No 34 Plot No 170Open Space00000
Row House No 35 Plot No 171Closed/Covered00000
Row House No 35 Plot No 171Open Space00000
Row House No 36 Plot No 172Closed/Covered00000
Row House No 36 Plot No 172Open Space00000
Row House No 37 Plot No 173Closed/Covered00000
Row House No 37 Plot No 173Open Space00000
Row House No 38 Plot No 174Closed/Covered00000
Row House No 38 Plot No 174Open Space00000
Row House No 39 Plot No 175Closed/Covered00000
Row House No 39 Plot No 175Open Space00000
Row House No 40 Plot No 176Closed/Covered00000
Row House No 40 Plot No 176Open Space00000
Row House No 41 Plot No 177Closed/Covered00000
Row House No 41 Plot No 177Open Space00000
Row House No 42 Plot No 178Closed/Covered00000
Row House No 42 Plot No 178Open Space00000
Row House No 43 Plot No 137Closed/Covered00000
Row House No 43 Plot No 137Open Space00000
Row House No 44 Plot No 138Closed/Covered00000
Row House No 44 Plot No 138Open Space00000
Row House No 45 Plot No 139Closed/Covered00000
Row House No 45 Plot No 139Open Space00000
Row House No 46 Plot No 140Closed/Covered00000
Row House No 46 Plot No 140Open Space00000
Row House No 47 Plot No 141Closed/Covered00000
Row House No 47 Plot No 141Open Space00000
Row House No 48 Plot No 142Closed/Covered00000
Row House No 48 Plot No 142Open Space00000
Row House No 49 Plot No 143Closed/Covered00000
Row House No 49 Plot No 143Open Space00000
Row House No 50 Plot No 144Closed/Covered00000
Row House No 50 Plot No 144Open Space00000
Row House No 51 Plot No 145Closed/Covered00000
Row House No 51 Plot No 145Open Space00000
Row House No 52 Plot No 146Closed/Covered00000
Row House No 52 Plot No 146Open Space00000
Row House No 53 Plot No 147Closed/Covered00000
Row House No 53 Plot No 147Open Space00000
Row House No 54 Plot No 150Closed/Covered00000
Row House No 54 Plot No 150Open Space00000
Row House No 55 Plot No 151Closed/Covered00000
Row House No 55 Plot No 151Open Space00000
Row House No 56 Plot No 152Closed/Covered00000
Row House No 56 Plot No 152Open Space00000
Row House No 57 Plot No 153Closed/Covered00000
Row House No 57 Plot No 153Open Space00000
Row House No 58 Plot No 154Closed/Covered00000
Row House No 58 Plot No 154Open Space00000
Row House No 59 Plot No 155Closed/Covered00000
Row House No 59 Plot No 155Open Space00000
Row House No 60 Plot No 156Closed/Covered00000
Row House No 60 Plot No 156Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Row House No 01 Plot No 12

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 02 Plot No 13

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 03 Plot No 118

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 04 Plot No 119

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 05 Plot No 120

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 06 Plot No 121

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 07 Plot No 122

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 08 Plot No 123

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 09 Plot No 124

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 10 Plot No 125

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 11 Plot No 126

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 12 Plot No 127

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 13 Plot No 128

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 14 Plot No 129

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 15 Plot No 130

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 16 Plot No 131

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 17 Plot No 132

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 18 Plot No 133

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 19 Plot No 134

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 20 Plot No 135

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 21 Plot No 136

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 22 Plot No 136

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 23 Plot No 158

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 24 Plot No 159

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 25 Plot No 160

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 26 Plot No 160

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 27 Plot No 161

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 28 Plot No 162

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 29 Plot No 163

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 30 Plot No 164

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 31 Plot No 165

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 32 Plot No 168

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 33 Plot No 169

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 34 Plot No 170

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 35 Plot No 171

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 36 Plot No 172

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 37 Plot No 173

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 38 Plot No 174

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 39 Plot No 175

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 40 Plot No 176

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 41 Plot No 177

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 42 Plot No 178

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 43 Plot No 137

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 44 Plot No 138

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 45 Plot No 139

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 46 Plot No 140

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 47 Plot No 141

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 48 Plot No 142

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 49 Plot No 143

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 50 Plot No 144

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 51 Plot No 145

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 52 Plot No 146

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 53 Plot No 147

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 54 Plot No 150

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 55 Plot No 151

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 56 Plot No 152

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 57 Plot No 153

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 58 Plot No 154

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 59 Plot No 155

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 60 Plot No 156

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyAS per norms0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)As per norms0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAs per norms0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationAS per norms0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

53 documents held by Deedo, 70 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • a Details of encumbrances concerned to FinanceNo Encumbrance Financial_0001.pdf · uploaded 1 May 2024View
  • a Details of encumbrances concerned to FinanceNo Encumbrance Legal_0001.pdf · uploaded 1 May 2024View
  • b Details of encumbrances concerned to LegalNo Encumbrance Financial_0001.pdf · uploaded 1 May 2024View
  • b Details of encumbrances concerned to LegalNo Encumbrance Legal_0001.pdf · uploaded 1 May 2024View
  • Copy of Layout Approval (in case of layout)1 Giridhar Sangi.pdf · uploaded 1 May 2024View
  • Building Plan Approval / NA Order for plotted development2 Giridhar Sangi.pdf · uploaded 1 May 2024View
  • Building Plan Approval / NA Order for plotted development3 Giridhar Sangi.pdf · uploaded 1 May 2024View
  • Building Plan Approval / NA Order for plotted development4 Giridhar Sangi.pdf · uploaded 1 May 2024View
  • Commencement Certificates / NA Order for plotted developmentGIRDHAR SANGI PERMISSION_0001_240422_170408.pdf · uploaded 1 May 2024View
  • Declaration about Commencement CertificateDeclaration About Commencement Certificate Giridhar.pdf · uploaded 1 May 2024View
  • Declaration in FORM BForm B declaiaration_0001.pdf · uploaded 1 May 2024View
  • Proforma of Agreement for saleAgreement to sale Flat_0001.pdf · uploaded 1 May 2024View
  • Proforma of Allotment letterAllotment Letter Flat_0001.pdf · uploaded 1 May 2024View
  • Deviation Report with respect to Allotment letterDeviation Allotment Flat_0001.pdf · uploaded 1 May 2024View
  • Deviation Report with respect to model copy of AgreementDeviation ATS Apartment_0001.pdf · uploaded 1 May 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsINTEREST IN OTHER ASHWINI_0001_240502_142936.pdf · uploaded 2 May 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsINTREST IN OTHER KAMLESH_0001_240502_142909.pdf · uploaded 2 May 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsINTREST IN OTHER REKHA_0001_240502_142824.pdf · uploaded 2 May 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsINTREST IN OTHER UTTAM_0001_240502_143001.pdf · uploaded 2 May 2024View
  • Other – LegalRow House No Mismatch Giridhar.pdf · uploaded 4 May 2024View
  • Other – TechnicalOrder No 50 Giridhar.pdf · uploaded 4 May 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate girdhar_0001 (1).pdf · uploaded 7 May 2024View
  • Commencement Certificates / NA Order for plotted developmentGiridhar Sangi Mail Verify.pdf · uploaded 7 May 2024View
  • Other – TechnicalGiridhar Sangi Mail Verify.pdf · uploaded 7 May 2024View
  • CERSAI detailsCERSAI_Search_Report_200305966974_For_Asset_Based_Search_07_05_2024_13_37_08_941.pdf · uploaded 7 May 2024View
  • CERSAI detailsCERSAI DECLARATION GIRIDHAR.pdf · uploaded 7 May 2024View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Declaration Giridhar.pdf · uploaded 7 May 2024View
  • Other – Technicalilovepdf_merged (52).pdf · uploaded 7 Jun 2024View
  • Other – FinanceCount of units.pdf · uploaded 14 Jun 2024View
  • Copy of the legal title reportSearch New Tirumala Bacchewar Sir Nanded.pdf · uploaded 5 Jul 2024View
  • Commencement Certificates / NA Order for plotted development2 Commencement Certificates _ NA Order for plotted development (35).pdf · uploaded 5 Jul 2024View
  • Other – Technical2 Commencement Certificates _ NA Order for plotted development (35).pdf · uploaded 5 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects Certificate Civil GI 05-01-25.pdf · uploaded 24 Jan 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate Civil GI 05-01-25.pdf · uploaded 24 Jan 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Civil.pdf · uploaded 3 Apr 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate Civil GI.pdf · uploaded 3 Apr 2025View
  • Disclosure of sold/ booked inventoryCivil Sold Book Inventory.pdf · uploaded 4 Apr 2025View
  • Form 1Form 1.pdf · uploaded 11 Jul 2025View
  • Form 2Form 2.pdf · uploaded 11 Jul 2025View
  • Disclosure of Sold and Booked InventoryCW Sold Book Inventory.pdf · uploaded 11 Jul 2025View
  • Form 1Form 1.pdf · uploaded 11 Jul 2025View
  • Form 2Form 2.pdf · uploaded 11 Jul 2025View
  • Disclosure of Sold and Booked InventoryCW Sold Book Inventory.pdf · uploaded 11 Jul 2025View
  • Form 1Form 1.pdf · uploaded 11 Jul 2025View
  • Form 2Form 2.pdf · uploaded 11 Jul 2025View
  • Disclosure of Sold and Booked InventoryCW Sold Book Inventory.pdf · uploaded 11 Jul 2025View
  • Form 1Form 1.pdf · uploaded 11 Jul 2025View
  • Form 2Form 2.pdf · uploaded 11 Jul 2025View
  • Disclosure of Sold and Booked InventoryCW Sold Book Inventory.pdf · uploaded 11 Jul 2025View
  • Form 1Architect Certificate.pdf · uploaded 10 Oct 2025View
  • Form 2Engineers Certificate Civil GI.pdf · uploaded 10 Oct 2025View
  • Disclosure of Sold and Booked InventoryCW Sold Book Inventory.pdf · uploaded 10 Oct 2025View
  • Form 1Form 1.pdf · uploaded 3 Jan 2026View
  • Form 2Form 2.pdf · uploaded 3 Jan 2026View
  • Disclosure of Sold and Booked Inventoryinventory 007.pdf · uploaded 3 Jan 2026View
  • Form 1Civil Work Architects Certifcate 3 (1).pdf · uploaded 9 Apr 2026View
  • Form 2Civil Work Engineers Certificate 3 (1).pdf · uploaded 9 Apr 2026View
  • Disclosure of Sold and Booked InventoryCivil work Sold Book Inventory March 26 3.pdf · uploaded 9 Apr 2026View
  • Form 1FORM1_11zon.pdf · uploaded 13 Jul 2026View
  • Form 2FORM2_11zon.pdf · uploaded 13 Jul 2026View
  • Disclosure of Sold and Booked InventorySOLD INVENTORY.pdf · uploaded 13 Jul 2026View

Promoter documents

  • Declaration Form BForm B declaiaration_0001.pdf · uploaded 1 May 2024View
  • Legal Title reportSearch New Tirumala Bacchewar Sir Nanded.pdf · uploaded 5 Jul 2024View

Technical documents

  • Layout Approval1 Giridhar Sangi.pdfView
  • Building Plan Approval2 Giridhar Sangi.pdfView
  • Building Plan Approval3 Giridhar Sangi.pdfView
  • Building Plan Approval4 Giridhar Sangi.pdfView

Other legal documents

  • Other – LegalRow House No Mismatch Giridhar.pdfView

Financial documents

  • Other – FinanceCount of units.pdf · uploaded 14 Jun 2024View

Proforma allotment letter

  • Proforma allotment letterAllotment Letter Flat_0001.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nanded Waghala (M Corp.), Nanded taluka

Survey, CTS, gat or plot numbers

118 to 14713150 to 155 158 to 165168 to 178Plots No 12Sy No. 38/A/1/1

As published on MahaRERA's project page

Plots No 12,13,118 to 147,150 to 155 158 to 165, 168 to 178, Sy No. 38/A/1/1, situated at mauje Wadi(BK), Nanded 413605

Boundaries

North
plot
South
Plot
East
Road
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKadge and Associates Arch Ravi Kadge—
Chartered accountantS P Partani and Co CA Shailesh Partani—
EngineerKadge and Associates Arch Ravi Kadge—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology