Raj Commercial Cum Residentail Building G -F

Completed

Nanded Waghala (M Corp.), Nanded 431605 |Promoter: Mr Sanjay Balaprasad Biyani

1 Sep 2017Registered with MahaRERA
25 Mar 2019Promised completion
3Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Buildings
3
Unit types
Commercial, Residential0 units in all
Land area for this project
3,629 sq m (39,064 sq ft)
Permissible built-up area
4,814 sq m (51,815 sq ft)
Sanctioned built-up area
3,864 sq m (41,589 sq ft)
Address
S No 39 Cts No 10056PIN 431605
Designated bank account
The Shamrao Vithal Cooperative Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.20670, 77.29798
Raj Commercial Cum Residentail Building G -F is at latitude 19.20670, longitude 77.29798.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 25 Mar 2019

The latest completion date on record passed 7 years and 7 months ago.

Registered
1 Sep 2017
Promised
25 Mar 2019

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P511000123231 Sep 201725 Mar 2019—Mr Sanjay Balaprasad BiyaniProject page

3 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building F60
Building G60
Commercial60

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Commercial · 0 unitsResidential · 0 units
BuildingTypeCarpet areaUnits
Building FCommercial1,058 sq m · 11,388 sq ft0
Building FResidential1,828 sq m · 19,676 sq ft0
Building GCommercial1,058 sq m · 11,388 sq ft0
Building GResidential1,828 sq m · 19,676 sq ft0
CommercialCommercial1,058 sq m · 11,388 sq ft0
CommercialResidential1,828 sq m · 19,676 sq ft0

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Building FClosed/Covered00000
Building FOpen Space000015
Building GClosed/Covered00000
Building GOpen Space000020
CommercialClosed/Covered00000
CommercialOpen Space000015

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Building F

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure70%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
  • Sanitary Fittings within the flats / premises40%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Building G

  • Excavation100%
  • Basement (if any)80%
  • Podiums (if any)0%
  • Plinth80%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises80%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Commercial

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure70%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
  • Sanitary Fittings within the flats / premises40%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyBORE WELL100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEWERAGE LINE100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingWORK NOT STARTED0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsWORK NOT STARTED0%
  • Electrical meter room, sub-station, receiving stationWORK IN PROGRESS0%
  • Aggregate area of recreational Open SpaceBUILDING BACK SIDE10%
  • Open Parking5050%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

12 documents held by Deedo, 16 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Copy of the legal title report007.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)007.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)imagetopdf(13).pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)imagetopdf(14).pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)007.pdf · uploaded 31 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentUntitled-13.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM Bimagetopdf(15).pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterimagetopdf(16).pdf · uploaded 31 Jul 2017View
  • Details of encumbrancesUntitled-14.pdf · uploaded 31 Jul 2017View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentRAJ G F.pdf · uploaded 14 Jan 2020View
  • Architect’s Certificate on Completion of Project (Form 4)RAJ G F.pdf · uploaded 14 Jan 2020View

Promoter documents

  • Legal Title report007.pdf · uploaded 31 Jul 2017View
  • Declaration Form Bimagetopdf(15).pdf · uploaded 31 Jul 2017View

Technical documents

  • Layout Approval007.pdfView
  • Building Plan Approval007.pdfView

Proforma allotment letter

  • Proforma allotment letterimagetopdf(16).pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nanded Waghala (M Corp.), Nanded taluka

Survey, CTS, gat or plot numbers

1005639S NO 39 CTS NO 10056

As published on MahaRERA's project page

S NO 39 CTS NO 10056

Boundaries

North
Road D B Patil And Yogeshwara Apartment
South
Road Deshmukh And Other Plot
East
Shendarkar House
West
Bhagwansingh Thakur Dr Hembade Debadwar Other

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Ganesh S More—
EngineerPankaj Zaware—

Source: MahaRERA project page. Contact details are not shown.