Gokuldham City Part A

Active

Nanded Waghala (M Corp.), Nanded 431602 |Promoter: Rama Developers

Residential / Group HousingRERAP51100020534
18 Apr 2019Registered with MahaRERA
30 Dec 2030Promised completion
35Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Active
Buildings
35
Land area for this project
4,189 sq m (45,093 sq ft)
Permissible built-up area
3,356 sq m (36,126 sq ft)
Sanctioned built-up area
3,356 sq m (36,121 sq ft)
Recreational open space
1,277 sq m (13,741 sq ft)
Planning authority
Nnaded Waghala City Muncipalty
Address
Gut No 4, Kautha, Near Ravi NagarPIN 431602
Designated bank account
Union Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.02995, 0.01099
Gokuldham City Part A is at latitude 0.02995, longitude 0.01099.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2030

Registered
18 Apr 2019
Promised
30 Dec 2030

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5110002053418 Apr 201930 Dec 2030—Rama DevelopersProject page

35 buildings

Buildings and wings named in the registration

Show all 35 buildingsShow fewer buildings

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Row House An 1Closed/Covered01001
Row House An 1Open Space00000
Row House Bn 2Closed/Covered01001
Row House Bn 2Open Space00000
Row House Bn 3Closed/Covered00000
Row House Bn 3Open Space00000
Row House Bn 4Closed/Covered00000
Row House Bn 4Open Space00000
Show all 70 parking rowsShow fewer parking rows
BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Row House Bn 5Closed/Covered00000
Row House Bn 5Open Space00000
Row House Cw 6Closed/Covered00000
Row House Cw 6Open Space00000
Row House Dw 10Closed/Covered00000
Row House Dw 10Open Space00000
Row House Dw 11Closed/Covered00000
Row House Dw 11Open Space00000
Row House Dw 12Closed/Covered00000
Row House Dw 12Open Space00000
Row House Dw 13Closed/Covered00000
Row House Dw 13Open Space00000
Row House Dw 7Closed/Covered00000
Row House Dw 7Open Space00000
Row House Dw 8Closed/Covered00000
Row House Dw 8Open Space00000
Row House Dw 9Closed/Covered00000
Row House Dw 9Open Space00000
Row House Ew 14Closed/Covered00000
Row House Ew 14Open Space00000
Row House Fw 15Closed/Covered00000
Row House Fw 15Open Space00000
Row House Ge 34Closed/Covered00000
Row House Ge 34Open Space00000
Row House He 35Closed/Covered00000
Row House He 35Open Space00000
Row House Ie 36Closed/Covered00000
Row House Ie 36Open Space00000
Row House Ie 37Closed/Covered00000
Row House Ie 37Open Space00000
Row House Ie 38Closed/Covered00000
Row House Ie 38Open Space00000
Row House Ie 39Closed/Covered00000
Row House Ie 39Open Space00000
Row House Ie 40Closed/Covered00000
Row House Ie 40Open Space00000
Row House Ie 41Closed/Covered00000
Row House Ie 41Open Space01001
Row House Ie 42Closed/Covered00000
Row House Ie 42Open Space00000
Row House Je 43Closed/Covered00000
Row House Je 43Open Space00000
Row House Kw 44Closed/Covered00000
Row House Kw 44Open Space00000
Row House Lw 45Closed/Covered00000
Row House Lw 45Open Space00000
Row House Lw 46Closed/Covered00000
Row House Lw 46Open Space00000
Row House Lw 47Closed/Covered00000
Row House Lw 47Open Space00000
Row House Lw 48Closed/Covered00000
Row House Lw 48Open Space00000
Row House Mw 49Closed/Covered00000
Row House Mw 49Open Space00000
Row House Mw 50Closed/Covered00000
Row House Mw 50Open Space00001
Row House Mw 51Closed/Covered00000
Row House Mw 51Open Space00000
Row House Nw 52Closed/Covered00000
Row House Nw 52Open Space00000
Row House Ow 53Closed/Covered00000
Row House Ow 53Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Row House An 1

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House Bn 2

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House Bn 3

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Show all 36 buildings and common areasShow fewer buildings and common areas

Row House Bn 4

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Bn 5

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Cw 6

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
  • Sanitary Fittings within the flats / premises20%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Row House Dw 10

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
  • Sanitary Fittings within the flats / premises20%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Row House Dw 11

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Dw 12

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Dw 13

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Dw 7

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Dw 8

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Dw 9

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Ew 14

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure50%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
  • Sanitary Fittings within the flats / premises10%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Row House Fw 15

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure50%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
  • Sanitary Fittings within the flats / premises10%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Row House Ge 34

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure50%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
  • Sanitary Fittings within the flats / premises10%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Row House He 35

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
  • Sanitary Fittings within the flats / premises10%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Row House Ie 36

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Ie 37

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Ie 38

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Ie 39

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Ie 40

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Ie 41

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Ie 42

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Je 43

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Kw 44

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Lw 45

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Lw 46

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Lw 47

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
  • Sanitary Fittings within the flats / premises10%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Row House Lw 48

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
  • Sanitary Fittings within the flats / premises10%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Row House Mw 49

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises10%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Row House Mw 50

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
  • Sanitary Fittings within the flats / premises10%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Row House Mw 51

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure50%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
  • Sanitary Fittings within the flats / premises10%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Row House Nw 52

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House Ow 53

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Common areas and amenities

  • Internal Roads & FootpathsWORK IN PROGRESS80%
  • Water Supplycompleted100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)completed100%
  • Storm Water Drainscompleted100%
  • Landscaping & Tree PlantingWORK IN PROGRESS20%
  • Street LightingWORK IN PROGRESS50%
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvesting0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementswork to be started0%
  • Electrical meter room, sub-station, receiving station0%
  • Aggregate area of recreational Open SpaceWORK IN PROGRESS0%
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

52 documents held by Deedo, 58 filings listed on MahaRERA's project page

Encumbrance details

Commencement certificate

Form B

Form 5 (6)

Show all 110 documentsShow fewer documents

Form 5 (6)

Title report

Form 1 (11)

Form 2 (11)

Form 2A (8)

Other (6)

Registration certificate

Layout plan

Building plan (3)

Allotment letter

Document library

  • Declaration in FORM BForm B.pdf · uploaded 9 Apr 2019View
  • Details of encumbrancesDeclaration.pdf · uploaded 9 Apr 2019View
  • Commencement Certificates / NA Order for plotted developmentBild Permission.pdf · uploaded 9 Apr 2019View
  • Certificates of CA (Form 5)CA Certificate.pdf · uploaded 9 Apr 2019View
  • Building Plan Approval (IOD)3-3.pdf · uploaded 9 Apr 2019View
  • Copy of Layout Approval (in case of layout)lay out map.pdf · uploaded 9 Apr 2019View
  • Building Plan Approval (IOD)2-3.pdf · uploaded 9 Apr 2019View
  • Building Plan Approval (IOD)1-3.pdf · uploaded 9 Apr 2019View
  • Proforma of Allotment letterविक्री करारनामा.pdf · uploaded 11 Apr 2019View
  • Copy of the legal title reportKautha Search Report.pdf · uploaded 12 Apr 2019View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Gokuldham City Part A , Form 1.pdf · uploaded 10 Feb 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Gokuldham City Part A , Form 2A.pdf · uploaded 10 Feb 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Gokuldham City Part A Engg.pdf · uploaded 10 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 2020-21.pdf · uploaded 10 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 2021-22.pdf · uploaded 10 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 2019-20.pdf · uploaded 10 Feb 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Gokuldham_City_Form_-_1_Architect;s_Certificate[1].pdf · uploaded 18 Feb 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGG CIRTIFICATE PART-A.pdf · uploaded 19 May 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CIRTIFICATE PART-A.pdf · uploaded 19 May 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A PART-A.pdf · uploaded 19 May 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Certificate Gokuldham City A.pdf · uploaded 22 Jul 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form - 2A - Engineer's Certificate (Quality Assurance) Q4 Part-A.pdf · uploaded 22 Jul 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer cetificate Q1 Part A 23-24.pdf · uploaded 22 Jul 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Certificate Gokuldham City A Q2 23-24.pdf · uploaded 28 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Egineer cetificate Q2 Part A 23-24.pdf · uploaded 28 Apr 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form - 2A - Engineer's Certificate (Quality Assurance) Q2 A.pdf · uploaded 28 Apr 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Certificate Gokuldham City A Q2 23-24.pdf · uploaded 28 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Egineer cetificate Q3 Part A 23-24.pdf · uploaded 28 Apr 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form - 2A - Engineer's Certificate (Quality Assurance) Q3 A.pdf · uploaded 28 Apr 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Certificate Gokuldham City A Q3 23-24.pdf · uploaded 12 Jun 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects Certificate Part A Q4-23-24.pdf · uploaded 14 Jun 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate Q4 23-24.pdf · uploaded 14 Jun 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form - 2A - Engineer's Certificate (Quality Assurance) Gokuldham City A Q4 23-24.pdf · uploaded 18 Jun 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architects Certificate Par A.pdf · uploaded 3 Aug 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2A Part A.pdf · uploaded 3 Aug 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate Par A.pdf · uploaded 3 Aug 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Part A.pdf · uploaded 3 Aug 2024View
  • Declaration about all RERA Designated Bank Accounts (Format A)Gokuldham City Part A Format A.pdf · uploaded 13 Nov 2024View
  • Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Gokuldham City Part A Format B (3).pdf · uploaded 13 Nov 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Certificate Gokuldham City B Q2.pdf · uploaded 16 Dec 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Certificate Gokuldham City A Q2 FY 24-25.pdf · uploaded 16 Dec 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer cetificate Q2 Part A 24-25.pdf · uploaded 16 Dec 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)form 5 part FY 22 23.pdf · uploaded 16 Dec 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 23 24.pdf · uploaded 16 Dec 2024View
  • Declaration about all RERA Designated Bank Accounts (Format A)format A Part A.pdf · uploaded 16 Dec 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Certificate Gokuldham City A Q4 FY 24-25.pdf · uploaded 18 Jul 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer cetificate Q4 Part A 24-25.pdf · uploaded 18 Jul 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form - 2A - Engineer's Certificate (Quality Assurance) Gokuldham City A Q4 24-25.pdf · uploaded 18 Jul 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Certificate Gokuldham City A Q1 FY 25-26.pdf · uploaded 18 Jul 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer cetificate Q1 Part A 25-26.pdf · uploaded 18 Jul 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form - 2A - Engineer's Certificate (Quality Assurance) Gokuldham City A Q1 25-26.pdf · uploaded 18 Jul 2025View

Promoter documents

  • Declaration Form BForm B.pdf · uploaded 9 Apr 2019View
  • Legal Title reportKautha Search Report.pdf · uploaded 12 Apr 2019View

Technical documents

  • Building Plan Approval3-3.pdfView
  • Building Plan Approval2-3.pdfView
  • Building Plan Approval1-3.pdfView
  • Layout Approvallay out map.pdfView

Proforma allotment letter

  • Proforma allotment letterविक्री करारनामा.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nanded Waghala (M Corp.), Nanded taluka

Survey, CTS, gat or plot numbers

GUT NO 4

As published on MahaRERA's project page

GUT NO 4

Boundaries

North
Remaining Part Of Gut No 4 Lay Out
South
Gut No 12
East
Gut No 05 Lay Out
West
Over Bridge

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShirish Purohit—
Chartered accountantShailesh Partani—
EngineerChaitanya Farkande—

Source: MahaRERA project page. Contact details are not shown.