Tower A and B · Pyramid City 6
Pipla · RERA P50500004036
IDBLD_00896310 floorsCompleted
10Sanctioned habitable floorsregistration certificate
30 Dec 2022Promised completion
Floors
10 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- Sanctioned habitable floors
- 10
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2 BHK | 70.1 m² (755 sq.ft) | 16 | not published |
| 2 BHK | 70.5 m² (758 sq.ft) | 12 | not published |
| 2 BHK | 70.7 m² (761 sq.ft) | 14 | not published |
| 2 BHK | 70.7 m² (761 sq.ft) | 4 | not published |
| 2 BHK | 71 m² (764 sq.ft) | 12 | not published |
| 2 BHK | 71.3 m² (767 sq.ft) | 4 | not published |
| Shop | 14.9 m² (161 sq.ft) | 3 | not published |
| Shop | 16.8 m² (181 sq.ft) | 1 | not published |
| Shop | 18.8 m² (202 sq.ft) | 2 | not published |
| Shop | 22.8 m² (245 sq.ft) | 1 | not published |
Show all 13 unit typesShow fewer unit types
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 24.5 m² (263 sq.ft) | 1 | not published |
| Shop | 25.7 m² (277 sq.ft) | 4 | not published |
| Shop | 32.1 m² (345 sq.ft) | 2 | not published |
| Total | 76 |
Parking
Spaces as declared on MahaRERA's project page.
| Type | Two-wheeler | Four-wheeler | Visitor | Total |
|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 1 |
| Open Space | 0 | 0 | 0 | 63 |
Construction progress
Work completed on this building, as the promoter reported it to MahaRERA (Form 1).
- Excavation100%
- Basement (if any)100%
- Podiums (if any)0%
- Plinth100%
- Stilt Floor100%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
- Sanitary Fittings within the flats / premises100%
Show all 11 activitiesShow fewer activities
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through9 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology