RERA projects in Katol (M Cl)
24 projects under 24 MahaRERA registrations, registered 2020–2026. 38% have a completion date extended beyond the one promised.
Locality
24RERA projects
24Registrations
19Completion still due5 past their completion date
4 monthsMedian extension beyond promised date38% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2020 | 2 |
| 2021 | 1 |
| 2022 | 0 |
| 2023 | 11 |
| 2024 | 1 |
| 2025 | 4 |
| 2026 | 5 |
Projects in Katol (M Cl)
24 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Vallabh Vithal ViharM/s. Vallabh Vithal Developers | PP1190002602056 | 1 Oct 2026 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Indira ViharIndira Vihar | PP1190002601705 | 31 Aug 2026 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Maa Chandika DevelopersMaa Chandika Developers | PP1190002601137 | 13 Jul 2026 | 31 May 2031 | 30 Sep 2031 | Extended 4 mo | 0 |
| Devam NagarPritam Dilip Rewatkar | PP1190002600434 | 15 May 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| City CenterSakaar Builders & Developers | PC1190002501978 | 1 Jan 2026 | 31 Mar 2028 | 31 Jul 2028 | Extended 4 mo | 0 |
| Radhey GreenArchana Jakhotia, Kamalkishore Kapuriya HUF, Nandkishore Chandak HUF, Kapuriya Om Prakash, Radha Rathi & Radhadevi Chandak | PP1190002501418 | 10 Nov 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Talmale LayoutPrashant Nathhuji Talmale | PP1190002501153 | 9 Oct 2025 | 31 Mar 2030 | 31 Jul 2030 | Extended 4 mo | 0 |
| New Chandika NagariWasudeorao Anadrao Deshmukh | P50500080602 | 19 Jun 2025 | 31 Dec 2027 | 31 Dec 2027 | Not yet due | 0 |
| Balaji TownSurendra Ramchandra Mahakalkar & Vinod Purushottam Dhoble | P50500079534 | 10 Mar 2025 | 31 Dec 2027 | 31 Dec 2027 | Not yet due | 0 |
| Maa Chandika NagarWasudeorao Anadrao Deshmukh | P50500054396 | 18 Jan 2024 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Royal CityTarmal Infra | P50500053686 | 22 Nov 2023 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Elite JasmineNarendra Shivajirao Wagh | P50500053515 | 8 Nov 2023 | 31 May 2027 | 30 Sep 2027 | Extended 4 mo | 0 |
| Leela NagariYash Bhattad Nirmal Bhattad Pramod Gandhi | P50500053492 | 8 Nov 2023 | 31 Dec 2024 | 31 Dec 2024 | Promised date passed | 0 |
| Sai CityKiran Gaikwad, Arti Choudhari, Namaji Ali Ehsan Ali Jafari, Yunus Aysan Ali Jafari | P50500052314 | 9 Aug 2023 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Vrindavan ViharGopal Kapuriya, Archana Jakhotia, Leelabai Chandak, Abhishek Chandak, Manisha Taori, | P50500052309 | 9 Aug 2023 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| New TownSri Balaji Developers | P50500051094 | 29 May 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Gajanan NagriPramod Bagade, Parag Dakhore, Pravin Wankhede, Jivan Gaikwad, Chandrabhan Gajabhiye,Devendra Sathone | P50500050760 | 3 May 2023 | 30 Dec 2026 | 30 Dec 2026 | Not yet due | 0 |
| Ayodhaya NagriBalaji Kavhar, Bijay Dagdiya, Rameshwar Bajad, Laxman Gawande, Vinod Gote | P50500050708 | 28 Apr 2023 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Shrawan WadiShree Ganesh Developers | P50500050508 | 17 Apr 2023 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| P.m.a.y. Scheme Tower A1 42 Ewsdewlling Unit City Survey No 806 Tah Katol Distt NagpurP.m.a.y. Muncipal Council Katol | P50500050129 | 20 Mar 2023 | 25 Aug 2024 | — | Promised date passed | 0 |
| Shantam NagriLotus Infraspace Developers | P50500049184 | 3 Feb 2023 | 31 Mar 2025 | 31 Mar 2025 | Promised date passed | 0 |
| Balaji NagarSanjay Yadavrao Charde | P50500030069 | 29 Jul 2021 | 30 Dec 2026 | 30 Dec 2026 | Not yet due | 0 |
| K K Chandak NagarPrakash Kasturchand Chandak | P50500024313 | 3 Feb 2020 | 30 Mar 2022 | 30 Mar 2022 | Promised date passed | 0 |
| Shubhash NagarShubhash Harishchandra Palsapure & Others | P50500024204 | 27 Jan 2020 | 30 Dec 2023 | 29 Dec 2024 | Extended 12 mo | 0 |
Other localities in Katol
Most active promoters
By projects registered here, as named on MahaRERA.
- Wasudeorao Anadrao Deshmukh2 projects
- Archana Jakhotia, Kamalkishore Kapuriya HUF, Nandkishore Chandak HUF, Kapuriya Om Prakash, Radha Rathi & Radhadevi Chandak1 project
- Balaji Kavhar, Bijay Dagdiya, Rameshwar Bajad, Laxman Gawande, Vinod Gote1 project
- Gopal Kapuriya, Archana Jakhotia, Leelabai Chandak, Abhishek Chandak, Manisha Taori,1 project
- Indira Vihar1 project
- Kiran Gaikwad, Arti Choudhari, Namaji Ali Ehsan Ali Jafari, Yunus Aysan Ali Jafari1 project
- Lotus Infraspace Developers1 project
- Maa Chandika Developers1 project
- M/s. Vallabh Vithal Developers1 project
- Narendra Shivajirao Wagh1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology