RERA projects in Bihalgondi

1 project under 2 MahaRERA registrations, registered 2025–2025. 100% have a completion date extended beyond the one promised.

Locality
1RERA projects
2Registrationssome projects hold several
2Completion still due0 past their completion date
4 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20252

Projects in Bihalgondi

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Crown CityBrijmohan Kishan Tiwari and Kirti GoyalPP1190002501432, PP119000250194611 Nov 202525 Dec 203525 Apr 2036Extended 4 mo0

Other localities in Katol

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Brijmohan Kishan Tiwari and Kirti Goyal1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology