Greenfield Layout 1

Its promised completion date, Apr 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record.

Hingna, Maharashtra 441110 · Promoter: L G Developers And Builders

Delivery3 yrs 6 mo past duePromised Apr 2023 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read
Greenfield Layout 1 project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Apr 2023, has passed and MahaRERA does not show it completed

  • This projectRegistered 18 May 2022, completion promised 30 Apr 2023, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.
Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP50500045378
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050004537818 May 202230 Apr 202330 Apr 2023L G Developers And BuildersProject page
Documents57

16 documents held by Deedo, 41 filings listed on MahaRERA's project page

Registration certificate

Other (7)

  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
Show all 57 documentsShow fewer documents

Commencement certificate (2)

  • Commencement certificateDate not statedView
  • Commencement certificateDate not statedView

Form 1 (3)

  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView

Title report

  • Title reportDate not statedView

Encumbrance details

  • Encumbrance detailsDate not statedView

Layout plan

  • Layout planDate not statedView

Legal

  • Legal Title reportLEGAL REPORT_compressed(1).pdf · uploaded 27 Apr 2022View
  • Declaration Form Baffidavit cum declaration_compressed.pdf · uploaded 3 May 2022View

Migrated

  • 1 Copy of the legal title reportLEGAL REPORT_compressed(1).pdf · uploaded 27 Apr 2022View
  • 1 Copy of Layout Approval (in case of layout)LAYOUT MAP_compressed.pdf · uploaded 27 Apr 2022View
  • 1 Building Plan Approval / NA Order for plotted developmentNA ORDER_compressed.pdf · uploaded 27 Apr 2022View
  • 1 Commencement Certificates / NA Order for plotted developmentNA ORDER_compressed.pdf · uploaded 27 Apr 2022View
  • 1 Declaration about Commencement Certificateaffidavit cum declaration_compressed.pdf · uploaded 27 Apr 2022View
  • 1 Proforma of Allotment letterAgreement Draft.pdf · uploaded 27 Apr 2022View
  • 1 PAN CardLG Pan Card-converted.pdf · uploaded 3 May 2022View
  • 1 Declaration in FORM Baffidavit cum declaration_compressed.pdf · uploaded 3 May 2022View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech's Certificate.pdf · uploaded 3 May 2022View
  • 1 Details of encumbrancesNo Encumbrance certificate.pdf · uploaded 5 May 2022View
  • 1 CERSAI detailsCERSAI_Search_Report.pdf · uploaded 5 May 2022View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)From 3 CA Certificate.pdf · uploaded 12 May 2022View
  • Form 1Form 130-06-2022.pdf · uploaded 20 Aug 2026Source
  • Form 2form 2 eng 30-06-2022.pdf · uploaded 20 Aug 2026Source
  • Form 3Form 3 30-06-2022.pdf · uploaded 20 Aug 2026Source
  • Disclosure of Sold and Booked Inventory30-06-2022.pdf · uploaded 20 Aug 2026Source
  • Form 1Form 1 30-09-2022.pdf · uploaded 20 Aug 2026Source
  • Form 2form 2 Eng 30-09-2022.pdf · uploaded 20 Aug 2026Source
  • Form 3Form 3 30-09-22.pdf · uploaded 20 Aug 2026Source
  • Disclosure of Sold and Booked Inventory30-09-2022.pdf · uploaded 20 Aug 2026Source
  • Form 1Form 1 31-12-2022.pdf · uploaded 20 Aug 2026Source
  • Form 2form 2 Eng 31-12-2022.pdf · uploaded 20 Aug 2026Source
  • Form 3Form 3 31-12-22.pdf · uploaded 20 Aug 2026Source
  • Disclosure of Sold and Booked Inventory31-12-2022.pdf · uploaded 20 Aug 2026Source
  • Form 1Form 131-03-2023.pdf · uploaded 20 Aug 2026Source
  • Form 2form 2 Eng 31-03-2023.pdf · uploaded 20 Aug 2026Source
  • Form 3Form 3 31-03-23.pdf · uploaded 20 Aug 2026Source
  • Disclosure of Sold and Booked Inventory31-03-2023.pdf · uploaded 20 Aug 2026Source
  • Form 1Form 1 30-06-2023.pdf · uploaded 20 Aug 2026Source
  • Form 2form 2 Eng 30-06-2023.pdf · uploaded 20 Aug 2026Source
  • Form 3Form 3 30-06-23.pdf · uploaded 20 Aug 2026Source
  • Disclosure of Sold and Booked Inventory30-06-2023.pdf · uploaded 20 Aug 2026Source
  • Form 2A (FY 2022-2023)1_Form 2A 31-03-2023.pdf · uploaded 20 Aug 2026Source
  • Form 2A (FY 2023-2024)2_Form 2A 31-03-2024.pdf · uploaded 20 Aug 2026Source
  • Form 5 (FY 2022-2023)Form 5 31-03-23 LG_0001 (1).pdf · uploaded 24 Aug 2026Source
  • Form 5 (FY 2023-2024)Form 5 30-09-23 L G_0001 (1).pdf · uploaded 24 Aug 2026Source

Technical

  • DocumentLAYOUT MAP_compressed.pdf · uploaded 27 Apr 2022View
  • DocumentNA ORDER_compressed.pdf · uploaded 27 Apr 2022View

Technical (Architect)

  • DocumentArchitech's Certificate.pdf · uploaded 3 May 2022View

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals296/2 at Nagpur

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Certificate Signed
Address
296/2, Hingna Road, Near Ycce CollegePIN 441110
Village
Wanadongri, Hingna taluka
Designated bank account
66
Developed in phases
No

Survey, CTS, gat or plot numbers

296/2 at Nagpur

Boundaries

North
Kh No 296
South
Kh No 297
East
Kh No 298
West
Kh No 293

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals7

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPrashant Satpute—
ArchitectUmesh Lamge—
Chartered accountantRanjeet Mishra—
Chartered accountantSachin Kale—
EngineerKishor Nimje—
EngineerKishor Nimjee—
EngineerMunish Bhute—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology