Narayan Nagari
Deedo IDDP-NGP-TPPCIts promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.
Hingna, Nagpur 441110 · Promoter: Radha Madhav Infrastructures
Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 24 Feb 2023, completion promised 31 Dec 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP50500049788
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P50500049788 | 24 Feb 2023 | 31 Dec 2025 | 31 Dec 2025 | Radha Madhav Infrastructures | Project page |
Documents75
28 documents held by Deedo, 47 filings listed on MahaRERA's project page
Show all 75 documentsShow fewer documents
Other (5)
Title report
- Title reportDate not statedView
Layout plan (5)
Commencement certificate (2)
Form B
- Form BDate not statedView
Form 2
- Form 2Date not statedView
Legal
Migrated
- 1 PAN Card11zon_removed-pages-PDF.pdf · uploaded 27 Jan 2023View
- 1 a Details of encumbrances concerned to FinanceLegal Encumbrance.pdf · uploaded 27 Jan 2023View
- 1 b Details of encumbrances concerned to LegalLegal Encumbrance.pdf · uploaded 27 Jan 2023View
- 1 Copy of Layout Approval (in case of layout)Plan Vinay Sarda.pdf · uploaded 27 Jan 2023View
- 1 Building Plan Approval / NA Order for plotted developmentPlan Vinay Sarda.pdf · uploaded 27 Jan 2023View
- 1 Commencement Certificates / NA Order for plotted developmentCC Vinay Sarda.pdf · uploaded 27 Jan 2023View
- 1 Declaration about Commencement CertificateDCC.pdf · uploaded 27 Jan 2023View
- 1 Declaration in FORM BForm B.pdf · uploaded 27 Jan 2023View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 27 Jan 2023View
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 27 Jan 2023View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)NN F2A.pdf · uploaded 27 Jan 2023View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA NN.pdf · uploaded 27 Jan 2023View
- 1 Proforma of Agreement for saleATS NN (2)_11zon.pdf · uploaded 27 Jan 2023View
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameNN BANK.pdf · uploaded 27 Jan 2023Source
- 1 Deviation Report with respect to Allotment letterDev allotment_11zon.pdf · uploaded 27 Jan 2023Source
- 1 Deviation Report with respect to model copy of AgreementDev ATS.pdf · uploaded 27 Jan 2023View
- 1 Copy of the legal title reportNarayan Nagari Title Report 1.pdf · uploaded 8 Feb 2023View
- 1 CERSAI detailsCERSAI Narayan Nagari.pdf · uploaded 8 Feb 2023View
- 1 Disclosure of Interest in Other Real Estate OrganizationsIOP.pdf · uploaded 8 Feb 2023Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 8 Feb 2023Source
- 2 a Details of encumbrances concerned to Finance1 a Details of encumbrances concerned to Finance (2) (2).pdf · uploaded 17 Feb 2023View
- 2 b Details of encumbrances concerned to Legal1 a Details of encumbrances concerned to Finance (2) (2).pdf · uploaded 17 Feb 2023View
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)RMI CHARTERED CERIFICATE.pdf · uploaded 12 May 2023View
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)NN Arch Certificate July Sept 2023.pdf · uploaded 16 Oct 2023View
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)NN Engineer Certificate July Sep Qtr 2023.pdf · uploaded 16 Oct 2023View
- 1 Disclosure of sold/ booked inventoryNN Sold Inventory July Sept Qtr.pdf · uploaded 16 Oct 2023View
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERIFICATE NARAYAN NAGARI JULY SEPT_11zon.pdf · uploaded 16 Oct 2023View
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)NN Engineer Certificate July Sep Qtr 2023.pdf · uploaded 17 Oct 2023View
- 2 Disclosure of sold/ booked inventoryNN Sold Inventory July Sept Qtr.pdf · uploaded 17 Oct 2023View
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A.pdf · uploaded 17 Oct 2023View
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Narayan form 1.pdf · uploaded 18 Jan 2024View
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)narayan form 2.pdf · uploaded 18 Jan 2024View
- 3 Disclosure of sold/ booked inventorynarayan inventory.pdf · uploaded 18 Jan 2024View
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)RMI CA.pdf · uploaded 19 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Narayan Nagari ARCHITECT CERTIFICATE SIGN.pdf · uploaded 29 Apr 2024View
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 11 Jun 2024View
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE RMI.pdf · uploaded 11 Jun 2024View
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERIFICATE RMI.pdf · uploaded 11 Jun 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentNARANAGERI RMI.pdf · uploaded 11 Jun 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 11 Jun 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)RMI C A ANNUAL REPORT.pdf · uploaded 21 Oct 2024Source
Technical
Technical (Architect)
- DocumentForm 1.pdf · uploaded 11 Jun 2024View
Technical (Engineer)
- DocumentENGINEER CERTIFICATE RMI.pdf · uploaded 11 Jun 2024View
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsKhasara No.412/3, P.H.No 49
As registered with MahaRERA and published on its project page
- Project type
- Plotted
- Status on MahaRERA
- Certificate Signed
- Address
- Khasara No.412/3, P.H.No 49, Hingna, HingnaPIN 441110
- Village
- Hingna, Hingna taluka
- Designated bank account
- 109
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- plot
- South
- plot
- East
- plot
- West
- plot
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | P B Gohar | — |
| Chartered accountant | Ritesh Panpaliya | — |
| Engineer | P B Gohar | — |
Source: MahaRERA project page. Contact details are not shown.