Skip to content
Deedo home
Menu
BLD_006611Completed6 floors

R D Tower · R D Tower

Chalisgaon · RERA P49900023945

6Sanctioned habitable floorsregistration certificate
30 Dec 2022Promised completion

Floors

6 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P49900023945 · registered 14 Jan 2020
Promised completion
30 Dec 2022
Sanctioned habitable floors
6

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK37.1 m² (399 sq.ft)2not published
1BHK37.7 m² (406 sq.ft)2not published
1BHK41.6 m² (448 sq.ft)2not published
1BHK43.4 m² (468 sq.ft)2not published
2BHK46.1 m² (496 sq.ft)2not published
2BHK46.9 m² (505 sq.ft)2not published
2BHK49.1 m² (529 sq.ft)2not published
2BHK52.9 m² (569 sq.ft)2not published
Shop8.1 m² (87 sq.ft)1not published
Shop10.9 m² (118 sq.ft)4not published
Shop11.4 m² (123 sq.ft)1not published
Total22

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered0001
Open Space0000

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through9 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology