Company or firm · first RERA registration 2017

Yashodeep Engineers & Builders

Of 2 registrations whose promised date has arrived, 2 were never extended past it (100%).

Projects22 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delayNonewhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record

No registration has been extended past its RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Casa RIO Phase IP52100013113Chikhali Bk.Certificate Signed31 Jul 201831 Jul 2018On date
Casa Rio Phase IIP52100024679Pimpri Chinchawad (M Corp.)Certificate Signed10 Dec 202210 Dec 2022On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology