Company or firm · first RERA registration 2022
Wmi Real Estate Developers Llp
Of 1 registration whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 4 mo — the same as Maharashtra's 4 mo.
Projects15 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
5 registrations of 5 moved past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ashford RegalP51800047384 | Kurla | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Ashford RegalP51800047421 | Kurla | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
| Ashford RegalP51800048460 | Kurla | Certificate Signed | 31 Dec 2025 | 31 Dec 2027 | +24 mo |
| Ashford RegalPM1183032400064 | Kurla | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 mo |
| Ashford RegalPM1184042502545 | Kurla | Certificate Signed | 30 Jun 2031 | 30 Oct 2031 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology