Wmi Real Estate Developers Llp

Of 1 registration whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 4 mo — the same as Maharashtra's 4 mo.

Projects15 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Wmi Real Estate Developers Llp developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

5 registrations of 5 moved past the RERA date

Months late against the original RERA promise, per registration

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Ashford RegalP51800047384KurlaCertificate Signed31 Dec 202730 Apr 2028+4 mo
Ashford RegalP51800047421KurlaCertificate Signed30 Jun 202730 Oct 2027+4 mo
Ashford RegalP51800048460KurlaCertificate Signed31 Dec 202531 Dec 2027+24 mo
Ashford RegalPM1183032400064KurlaCertificate Signed30 Jun 202930 Oct 2029+4 mo
Ashford RegalPM1184042502545KurlaCertificate Signed30 Jun 203130 Oct 2031+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology