Company or firm · first RERA registration 2017
Westerncity Townships Llp
Of 2 registrations whose promised date has arrived, 0 were never extended past it (0%).
Projects22 RERA registrations
Kept RERA date0%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases1no insolvency
2 registrations of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Vtp Solitaire Phase 1 AbRegulatory order: PROJECT NAME:VTP SOLITAIRE PHASE 1 AB (Regulatory Case No.117 of 2023) dated 28 December 2023. | 28 Dec 2023 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Vtp Solitaire Phase 1 AbP52100000727 | Pashan | Certificate Signed | 30 Jun 2022 | 31 Oct 2023 | +16 mo |
| VTPSolitaire Building C AND DP52100022428 | Pashan | Certificate Signed | 30 Dec 2023 | 31 Dec 2024 | +12 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology