Company or firm · first RERA registration 2017
Vtp Corpartion Llp
Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 23 mo late.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay23 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Purvanchal Phase1 ABP52100001109 | Kesnand | Certificate Signed | 30 Jun 2021 | 29 Dec 2022 | +18 mo |
| Purvanchal F BuildingP52100021535 | Kesnand | Certificate Signed | 30 Jun 2024 | 29 Jun 2025 | +28 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology