Vtp Corpartion Llp

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 23 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay23 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Purvanchal Phase1 ABP52100001109KesnandCertificate Signed30 Jun 202129 Dec 2022+18 mo
Purvanchal F BuildingP52100021535KesnandCertificate Signed30 Jun 202429 Jun 2025+28 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology