Company or firm · first RERA registration 2021
Vl Savli Developers Llp
None of 3 registrations has reached its promised completion date yet.
Projects33 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Eastern Groves Phase 1AP51800028005 | Kurla | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
| Eastern Groves Phase 1BP51800028289 | Kurla | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
| Eastern Groves Phase 2P51800051916 | Hariyali | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology