Vl Gajamukh Developers Llp

Deedo IDDD-ACM0

Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects11 RERA registration
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency

No registration has run past its RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
Quarterly progress report not filedEast SydeQuarterly progress report not filed: East SydeNot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
East SydeP51800031002KurlaCertificate Signed31 Dec 202531 Dec 2025On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology