Vira Theatres Pvt Ltd

Deedo IDDD-3ZKW

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 44 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay44 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Mahavir Heights NxP51700008098DombivliCertificate Signed31 Jan 202130 Sep 2024+44 mo
Mahavir Sarvoday PlazaP51700025161KalyanCertificate Signed30 Mar 202630 Mar 2026On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology