Vinayak Kishor Garve

Of 4 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 19 mo late — longer than Maharashtra's 4 mo.

Projects34 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay19 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

4 registrations of 4 ran past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Golden Treasures Wing DP52100001147PunawaleCertificate Signed31 Dec 201930 Dec 2021+24 mo
Golden Treasures Wing BP52100001250PunawaleCertificate Signed18 Apr 201830 Jun 2019+14 mo
Golden TreasuresP52100001728PunawaleCertificate Signed18 Apr 201830 Jun 2019+14 mo
Golden TreasuresP52100001868PunawaleCertificate Signed31 Dec 201930 Dec 2021+24 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology