Individual promoter · first RERA registration 2017

Vilas Madanlal Kothari

Deedo IDDD-ARX2

Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

No registration has run past its RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Neel Sai GangaP52000000904PanvelCertificate Signed31 Mar 201931 Mar 2019On date
Neel SolitaireP52000026023PanvelCertificate Signed30 Jun 202530 Jun 2025On date
Neel HermitageP52000080768PanvelCertificate Signed31 Dec 202631 Dec 2026On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology