Company or firm · first RERA registration 2021
Vilas Javdekar Infinitee Developers Pvt. Ltd
Of 4 registrations whose promised date has arrived, 4 kept it (100%).
Projects811 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time329registered sale deeds
Regulatory cases0none on record
6 registrations of 11 ran past the RERA date
Months late against the original RERA promise, per registration
Show all 11 registrations
11 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| YashONE InfiniteeP52100028229 | Punawale | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | On date |
| YashONE InfiniteeP52100029042 | Punawale | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| YashONE Infinitee - Phase IIIP52100030825 | Punawale | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Yashone EterniteeP52100046122 | Man | Certificate Signed | 30 Apr 2026 | 30 Apr 2026 | On date |
| Yashwin Enchante Phase 1P52100046510 | Wagholi | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
| UK1321 Inclusive HousingP52100049638 | Wagholi | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Yashone EterniteeP52100052676 | Man | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
| Yashwin Urbo CentroP52100053194 | Wakad | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Yashwin Enchante Phase 2P52100077455 | Wagholi | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
| Yashwin Urbo CentroP52100077674 | Wakad | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 mo |
| Pratik Nagar Palladio Kothrud CentralPR1260002501660 | Kothrud | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
Show all 11 registrationsShow fewer
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology