Skip to content
Individual promoter · first RERA registration 2024

Vikram Sanjay Nimbalkar

None of 2 registrations has reached its promised completion date yet.

Projects12 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Vikram Sanjay Nimbalkar developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

1 registration of 2 moved past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Govind ParkP52700054856Kolki (Ct)Certificate Signed31 Aug 202731 Aug 2027On date
Govind ParkPM1300002501093Kolki (Ct)Certificate Signed27 Mar 203027 Jul 2030+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology