Vijaykamal Properties Pvt Ltd

Deedo IDDD-RYGH

None of 2 registrations has reached its promised completion date yet.

Projects22 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases1includes insolvency

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
Listed as an NCLT insolvency projectMeridian Court 1Listed as NCLT project: Meridian Court 1Not on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Meridian Court 1P51800007441BorivaliCertificate Signed31 Dec 202731 Dec 2027On date
West Center Meridian CourtPM1181012500995BorivaliCertificate Signed31 Dec 203030 Apr 2031+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology