Individual promoter · first RERA registration 2017

Vihang Ashok Shah

Deedo IDDD-7B8T

Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 6 mo late — longer than Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay6 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Anand Prospera C wingP53000000357Kolhapur (M Corp.)Certificate Signed15 May 201830 Nov 2018+6 mo
Anand Prospera B WingP53000015137Kolhapur (M Corp.)Certificate Signed30 Nov 202030 Nov 2020On date
Anand Chintamani Phase IIP53100030221Sangli Miraj Kupwad (M Corp.)Certificate Signed31 Dec 202431 Dec 2024On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology