Company or firm · first RERA registration 2025
VC Bace Constrotech LLP
Deedo IDDD-T8NQNone of 2 registrations has reached its promised completion date yet.
Projects22 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Gauri Nandan ApartmentsP52100079826 | Wadagaon (Ct) | Certificate Signed | 30 Dec 2027 | 30 Apr 2028 | +4 mo |
| SwarajyaPM1260002501991 | Wadagaon (Ct) | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology