Company or firm · first RERA registration 2017
Vastushilp
Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 107 mo late — longer than Maharashtra's 4 mo.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay107 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Nishigandh 1P52100013723 | Wagholi | Certificate Signed | 31 Mar 2019 | 31 Dec 2026 | +93 mo |
| SonchafaP52100008160 | Haveli | Certificate Signed | 31 Dec 2017 | 31 Dec 2027 | +120 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology