Company or firm · first RERA registration 2017

Vastu Developers And Builders

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 22 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay22 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Prathamesh Phase 2-Alankar ResidecyP52100013849Talegaon Dabhade (M Cl)Certificate Signed31 Mar 201831 Mar 2018On date
Vastu RajyogP52100027438Talegaon Dabhade (R)Certificate Signed30 Dec 202430 Dec 2024+22 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology