Individual promoter · first RERA registration 2019
Vardhman Ganpatlal Singhvi
Deedo IDDD-P7HSOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 22 mo late.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay22 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Nirvaana Business Park Phase IDeregistered: Nirvaana Business Park Phase I | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Nirvaana Business Park Phase IP99000019733 | Vasaivirar City (M Corp) | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +34 mo* |
| Nirvaana GreensP51800051885 | Kurla | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +10 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology