Company or firm · first RERA registration 2017
Vardhan Housing
Of 1 registration whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 4 mo — the same as Maharashtra's 4 mo.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases3no insolvency
1 registration of 1 moved past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Vardhan HeightsRegulatory order: PROJECT NAME: VARDHAN HEIGHTS (Regulatory Case No. 419 OF 2025) dated 14 Nov, 2025. | 14 Nov 2025 |
| Regulatory order | Vardhan HeightsRegulatory order: PROJECT NAME:VARDHAN HEIGHTS (Regulatory Case No. 273 OF 2024) dated 31 July 2024. | 31 Jul 2024 |
| Regulatory order | Vardhan HeightsRegulatory order: PROJECT NAME: VARDHAN HEIGHTS (Regulatory Case No. 22 of 2023) dated 18 May 2023. | 24 May 2023 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Vardhan HeightsP51800014198 | Kurla | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology