Company or firm · first RERA registration 2019
Vardhaman Venture
Deedo IDDD-05APOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 46 mo late.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay46 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| VARDHAMAN VATIKA PHASE iii BUILD NO 3P51700021541 | Sarmal | Certificate Signed | 30 Dec 2022 | 30 Jun 2023 | +46 mo* |
| Vardhaman Vatika Phase 3 Building No 4P51700051332 | Sarmal | Certificate Signed | 30 Jun 2028 | 30 Jun 2028 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology