Company or firm · first RERA registration 2018
Vadilal Creation
Deedo IDDD-7ZT8Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.
Projects13 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| ChanakyaP51700015655 | Nelje | Certificate Signed | 30 Apr 2022 | 30 Apr 2022 | +54 mo* |
| ChanakyaPR1330002501280 | Nelje | Certificate Signed | 31 Oct 2029 | 28 Feb 2030 | +4 mo |
| ChanakyaPR1330002501295 | Nelje | Certificate Signed | 30 Dec 2027 | 30 Apr 2028 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology