Company or firm · first RERA registration 2018

Vadilal Creation

Deedo IDDD-7ZT8

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.

Projects13 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
ChanakyaP51700015655NeljeCertificate Signed30 Apr 202230 Apr 2022+54 mo*
ChanakyaPR1330002501280NeljeCertificate Signed31 Oct 202928 Feb 2030+4 mo
ChanakyaPR1330002501295NeljeCertificate Signed30 Dec 202730 Apr 2028+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology