Company or firm · first RERA registration 2018
V M Homes Pvt Ltd
None of 2 registrations has reached its promised completion date yet.
Projects22 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
No registration has run past its RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Quarterly progress report not filed | Shree Sammet Shikhar HeightsQuarterly progress report not filed: SHREE SAMMET SHIKHAR HEIGHTS | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Sammet Shikhar HeightsP51900018338 | Ward Abcd | Certificate Signed | 30 Dec 2027 | 30 Dec 2027 | On date |
| Shree Sammet Shikhar Heights - C WingP51900054247 | Ward Abcd | Certificate Signed | 31 Dec 2028 | 31 Dec 2028 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology