Company or firm · first RERA registration 2017
V.M.Associates
Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 13 mo late — longer than Maharashtra's 4 mo.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay13 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Quarterly progress report not filed | Avirahi Homes Building No 4 Wing BQuarterly progress report not filed: AVIRAHI HOMES BUILDING NO 4 WING B | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Avirahi Homes Building 3P51800009582 | Borivali | Certificate Signed | 31 Dec 2018 | 30 Oct 2020 | +22 mo |
| Avirahi Homes Building No 4 Wing BP51800077443 | Borivali | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology