Uttam Park Land Developers
Of 3 registrations whose promised date has arrived, 3 were never extended past it (100%).
Projects23 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed3as reported on MahaRERA
Regulatory cases0none on record
No registration has been extended past its RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Uttam Town - Unit 1P50400013272 | Inzapur | Completed | 31 Jul 2018 | — | On date |
| Uttam Town UnitP50400013276 | Inzapur | Completed | 31 Aug 2018 | — | On date |
| Uttam Town UnitP50400013351 | Inzapur | Completed | 31 Jul 2018 | — | On date |