Urich Grace Infrastructure Pvt Ltd

Deedo IDDD-MEMZ

Of 3 registrations whose promised date has arrived, 3 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

No registration has run past its RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Rose GardenP50500003460RuiCompleted31 Mar 2019—On date
Hibiscus GardenP50500012509Gawasi ManapurCertificate Signed31 Mar 201931 Mar 2019On date
Hibiscus Garden Shopping ComplexP50500021681Gawasi ManapurCertificate Signed30 Jun 202230 Jun 2022On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology