Company or firm · first RERA registration 2025

Upsquare Ventures LLP

Deedo IDDD-01WA

None of 3 registrations has reached its promised completion date yet.

Projects23 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
SHUBH VEDA Tower E F G and Block 8P52100080358AkurdiCertificate Signed31 Dec 203031 Dec 2030On date
Shubh VedaP52100080707AkurdiCertificate Signed31 Dec 202830 Apr 2029+4 mo
Shubh VedaPR1263032601566AkurdiCertificate Signed31 Dec 203031 Dec 2030On date