Company or firm · first RERA registration 2025
Upsquare Ventures LLP
Deedo IDDD-01WANone of 3 registrations has reached its promised completion date yet.
Projects23 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| SHUBH VEDA Tower E F G and Block 8P52100080358 | Akurdi | Certificate Signed | 31 Dec 2030 | 31 Dec 2030 | On date |
| Shubh VedaP52100080707 | Akurdi | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Shubh VedaPR1263032601566 | Akurdi | Certificate Signed | 31 Dec 2030 | 31 Dec 2030 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology