Company or firm · first RERA registration 2018
Unique Super Infra Private Limited
Of 2 registrations whose promised date has arrived, 0 were never extended past it (0%).
Projects22 RERA registrations
Kept RERA date0%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Skyline JewelP52000015945 | Taloje Panchnad | Certificate Signed | 30 Sep 2020 | 30 Mar 2022 | +18 mo |
| Skyline JewelP52000021023 | Taloje Panchnad | Certificate Signed | 25 Jun 2021 | 31 Mar 2023 | +21 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology