Tulip Inn Construwell Pvt. Ltd

Deedo IDDD-J912

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 43 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay43 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Bhagyasthan Phase1P52100000316Talegaon Dabhade (M Cl)Certificate Signed30 Jun 20208 Jul 2024+76 mo*
Bhagyasthan PlottingP52100078382Talegaon Dabhade (M Cl)Certificate Signed31 Dec 202531 Dec 2025+10 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology