Company or firm · first RERA registration 2017
Triveni Lifestyle Developers Llp
Deedo IDDD-TYQ1Of 4 registrations whose promised date has arrived, 4 kept it (100%).
Projects44 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
No registration has run past its RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Triveni Majesta - Wing A - Phase IP51700003079 | Adharwadi | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Triveni Majesta B WingP51700021897 | Kalyandombivali (M Corp.) | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
| Triveni GrandeP51700029471 | Kalyan | Certificate Signed | 31 Mar 2024 | 31 Mar 2024 | On date |
| Triveni ClassicP51700030951 | Kalyandombivali (M Corp.) | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology