Company or firm · first RERA registration 2017

Trisha Developers

Of 8 registrations whose promised date has arrived, 8 were never extended past it (100%).

Projects1414 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Trisha Developers developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

5 registrations of 14 moved past the RERA date

Months late against the original RERA promise, per registration

Show all 14 registrations

14 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
SmrutiP52100006813Pune (M Corp.)Certificate Signed30 Dec 202130 Dec 2021On date
Shri Anand ShriP52100014402Pune (M Corp.)Certificate Signed30 Dec 202130 Dec 2021On date
RajyogshreeP52100016035KothrudCertificate Signed30 Dec 202230 Dec 2022On date
NirmalaP52100018072Pune (M Corp.)Certificate Signed30 Dec 202230 Dec 2022On date
Rahul ViharP52100025532HaveliCertificate Signed30 Jun 202430 Jun 2024On date
Shradha ApartmentP52100025898KothrudCertificate Signed30 Jun 202430 Jun 2024On date
PratibhaP52100029562HaveliCertificate Signed31 Dec 202331 Dec 2023On date
MadhujeevanP52100050388Pune (M Corp.)Certificate Signed31 Jan 202631 Jan 2026On date
SurekhaP52100054802KothrudCertificate Signed31 Jan 202831 May 2028+4 mo
SuvarnabanP52100077493Pune (M Corp.)Certificate Signed30 Jun 202830 Oct 2028+4 mo
Sumali Cooperative Housing Society LimitedPR1260002502745Erandwana NorthCertificate Signed31 Mar 202931 Jul 2029+4 mo
Navswati Co-operative Housing Society LtdPR1260002600524KothrudCertificate Signed31 Mar 202931 Jul 2029+4 mo
GurusevaPR1260002601254KothrudCertificate Signed31 Mar 202831 Jul 2028+4 mo
Anushree sahakari Gruhrachana Sanstha Maryadit.PR1260002602093Erandwane SouthCertificate Signed31 Dec 203031 Dec 2030On date