Skip to content
Company or firm · first RERA registration 2017

Trinity Developers

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 55 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay55 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Trinity Galaxy R1 and R4P51700007348Badlapur (M Cl)Certificate Signed30 Jun 201830 Jun 2018On date
Trinity Galaxy R5P51700021561Badlapur (M Cl)Certificate Signed30 Mar 202230 Mar 2022+55 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology