Tridhaatu Vishnu Kunj Developers LLP
Deedo IDDD-FQMNOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 97 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Tridhaatu AarohaP51900010312 | Mumbai City | Certificate Signed | 30 Sep 2018 | 31 Dec 2023 | +97 mo* |
Tridhaatu Vishnu Kunj Developers LLP, in questions
Does Tridhaatu Vishnu Kunj Developers LLP finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 97 mo late. Across Maharashtra, 73% kept their date.
How many projects has Tridhaatu Vishnu Kunj Developers LLP registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Tridhaatu Vishnu Kunj Developers LLP have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.