Company or firm · first RERA registration 2020

Trident Infracon

Deedo IDDD-9EGP

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 25 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay25 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Trident BlissP52000024566UlaweCertificate Signed30 Dec 202330 Dec 2023+34 mo*
Sai Amrut ParkP52000047869RodpaliCertificate Signed30 Jun 202530 Jun 2025+16 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology