Company or firm · first RERA registration 2017
Transcon-Sheth Creators Private Limited
Deedo IDDD-W0P0Of 5 registrations whose promised date has arrived, 2 kept it (40%). The rest ran a median 22 mo late.
Projects47 RERA registrations
Kept RERA date40%Maharashtra: 73%
Median delay22 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
5 registrations of 7 ran past the RERA date
Months late against the original RERA promise, per registration
7 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Auris BlissP51800000970 | Andheri | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | +22 mo* |
| Auris SerenityP51800001080 | Borivali | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Auris SerenityP51800001082 | Borivali | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | +22 mo* |
| Auris SerenityP51800001413 | Borivali | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Auris GalleriaP51800017171 | Andheri | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +34 mo* |
| Auris IlariaP51800028533 | Borivali | Certificate Signed | 30 Oct 2027 | 29 Feb 2028 | +4 mo |
| Auris IlariaP51800033238 | Borivali | Certificate Signed | 30 Apr 2028 | 30 Aug 2028 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology